Securing America’s New Energy Future
ASX Code
Investor Presentation
June 2025
QTCQX
JLL
JNDAF
jindaleelithium.com
Warning Statement
This Presentation has been prepared by Jindalee Lithium Limited (“Jindalee,”
“Company” or “JLL”) and is authorized for release by its Chief Executive Officer, Mr.
Ian Rodger. This presentation provides general background information about
Jindalee’s activities. That information is current at the date of this presentation and
remains subject to change without notice. Certain information in this presentation has
been derived from third parties and though Jindalee has no reason to believe that it is
not accurate, reliable, or complete, it has not been independently audited or verified
by Jindalee. Except to the extent required by law, Jindalee makes no representations
or warranty as to the accuracy, reliability, or completeness of information in this
document and does not take responsibility for updating any information or correcting
any errors or omissions which may become apparent after this presentation is
released.
This presentation is for information purposes only and is a summary and does not
purport to be complete nor does it contain all the information which would be required
in, nor is it, a prospectus, product disclosure statement, or other disclosure document
under Australian law or any other law (and will not be lodged with the Australian
Securities and Investments Commission or any foreign regulator) and is not, and does
not constitute, an invitation or offer of securities for subscription, purchase, or sale in
any jurisdiction. In particular, this presentation does not constitute an invitation or offer
of securities for subscription, purchase, or sale in the United States or any other
jurisdiction in which such an offer would be illegal. The securities referred to in this
presentation have not been and will not be registered under the U.S. Securities Act of
1933 as amended or the securities laws of any state or other jurisdiction of the United
States and may not be offered or sold, directly or indirectly in the United States.
Pre-Feasibility Study. The Pre-Feasibility Study, including the production target and
the forecast financial information derived from the production target, referred to in this
presentation (PFS) was first released to the ASX on 19 November 2024 (PFS
Announcement). This presentation includes summary excerpts from the PFS and
does not purport to be all-inclusive or complete and should be read together with the
PFS Announcement. The Company confirms that all material assumptions and
technical parameters underpinning the production target and the forecast financial
information derived from the production target, continue to apply and have not
materially changed.
Shareholders and prospective investors should be aware that the PFS and this
presentation does not include any forecast financial information in respect of the
period after the initial 40 years of the Processing Schedule (post single commission
and ramp up year), as Jindalee cannot, at this stage, provide forecast financial
information for that subsequent period.
All amounts are in US$ unless stated otherwise.
This presentation contains certain forward-looking statements, including forecast
financial information. Forward-looking statements include but are not limited to
statements concerning Jindalee’s current expectations, estimates, and projections
about the industry in which Jindalee operates and beliefs and assumptions regarding
Jindalee’s future performance. When used in this document, the words such as
“anticipate,” “could,” “plan,” “estimate,” “expects,” “seeks,” “intends,” “may,” “potential,”
“should,” and similar expressions are forward-looking statements. Although Jindalee
believes that that it has a reasonable basis for those forward looking statements and
forecast financial information, including the use of a flat US$24,000/t lithium carbonate
price in the PFS, the production target set out in this presentation and the financial
information based on it , such statements are subject to known and unknown risks,
uncertainties, and other factors, some of which are beyond the control of Jindalee and
no assurance can be given that actual results will be consistent with these forwardlooking statements. The basis for that conclusion is contained throughout the PFS
Announcement and all material assumptions, including the JORC modifying factors,
upon which the forward looking statements and forecast financial information are
based, are disclosed in the PFS Announcement and this presentation should be read
together with the PFS Announcement.
To achieve the range of outcomes indicated in the PFS, the PFS estimates that
funding in the order of $3.02B in construction capital will be required. Shareholders
and investors should be aware that there is no certainty that Jindalee will be able to
raise the required funding when needed and it is possible that such funding may only
be available on terms that may be highly dilutive or otherwise adversely affect
Jindalee shareholders’ exposure to the McDermitt Lithium Project (Project)
economics. Specifically, as outlined in the PFS Announcement, Jindalee intends to
pursue potential third party partnerships (with parties who have the potential to be
joint venture partners in the Project) to advance the Project and may pursue other
value realisation strategies such as a sale or partial sale of the Project or underlying
future commodity streams. If it does so, such arrangements may materially reduce
Jindalee’s proportionate ownership of the Project and/ or adversely affect Jindalee
shareholders’ exposure to the Project economics.
exploration programs and budgets based upon the results of exploration, future prices
of minerals resources; grade or recovery rates; accidents, labour disputes, and other
risks of the mining industry; delays in obtaining government approvals or financing or
in the completion of development or construction activities; movements in the share
price of investments and the timing and proceeds realized on future disposals of
investments, force majeure events, as well as those factors detailed in the PFS
Announcement or, from time to time, in the Company’s interim and annual financial
statements and reports, all of which are available for review on ASX at asx.com.au
and OTC Markets at otcmarkets.com.
Although the Company has attempted to identify important factors that could cause
actual actions, events or results to differ materially from those described in forwardlooking statements will prove to be accurate, as actual results and future events could
differ materially from those anticipated in such statements. Accordingly, readers
should not place undue reliance on forward-looking statements. To the extent
permitted by law, Jindalee and its officers, employees, related bodies corporate and
agents disclaim all liability, direct, indirect or consequential (and whether or not arising
out of the negligence, default, or lack of care of Jindalee and/or any of its agents) for
any loss or damage suffered by a recipient or other persons out of, or in connection
with, any use or reliance on this presentation or information. This presentation does
not constitute investment advice and has been prepared without taking into account
any investor's particular investment objectives, financial circumstances or particular
needs and the opinions and recommendations in this presentations are not intended
to represent recommendations of particular investments to particular persons. You
should seek professional advice when deciding if an investment is appropriate. All
securities transactions involve risks, which include (among others) the risk of adverse
or unanticipated market, financial or political developments.
Please refer to Appendix 5 for details of the Competent Persons Statement’s relating
to the Mineral Resources and Ore Reserves contained in this Presentation.
Statements in this presentation regarding the Company’s business, which are not
historical facts, are forward-looking statements that involve risks and uncertainties.
These include, among others, risks and uncertainties related to Mineral Resource and
Ore Reserve estimates, production targets, forecast financial information, lithium
carbonate prices, capital and operating costs, risks related to results of current or
planned exploration activities, changes in market conditions, obtaining appropriate
approvals to undertake exploration activities in the portfolio of projects, changes in
2
Pure play US lithium company
focused on giant McDermitt Project
Oregon
Key investment highlights:
View in Vrify
Globally Significant Lithium Resource in the US
One of the largest lithium resources in the US @ 21.5Mt LCE[2),
positioned as a strategic asset in meeting America’s critical mineral
needs.
Robust PFS Demonstrating Exceptional Economics(1)
Long-life, large-scale production of battery-grade lithium carbonate in
the bottom half of the industry cost curve.(A)
Strategically Positioned to Address Medium-Term Supply Deficit
With lithium prices at unsustainable levels and supply additions
slowing, McDermitt is well-positioned to support future supply needs as
demand continues to grow.
Thacker Pass Project
66.1Mt LCE(B)
Strong US Government Engagement and Support
One of 10 initial FAST-41 transparency projects, fast-tracking federal
permitting and coordination(3). Currently partnering with the US
Department of Energy via a Research and Development Agreement. (4)
Nevada
Transformative Year Ahead
Catalysing value with potential US government grant funding, strategic
partnerships, and permitting milestones.
(1) All information contained within JLL ASX release 19/11/2024 “McDermitt PFS - Multi-Decade Source of US
Lithium Carbonate.” (PFS Announcement) (2) JLL ASX release 27/02/2023 “Resource at McDermitt increases to
21.5 Mt LCE” (3) JLL ASX release 22/04/2025 “McDermitt Project Fast-Tracked Under U.S. FAST-41 Initiative”
(4) JLL ASX release 16/09/2024 “Jindalee Secures Strategic Agreement with US Department of Energy”
(A) Benchmark Mineral Intelligence 2030 C1 Lithium Carbonate Equivalent Cost Curve (Q3 2024 dataset). (B) See
appendix 2 for source and detailed breakdown of resource estimate
21.5Mt LCE
66%
63 year
Contained resource(2)
EBITDA margin over the
first 10 years
Project life
McDermitt Recognised as a
FAST-41 Transparency Project
One of the First 10 Mining Projects Initially Added as FAST-41
Transparency Projects
What is FAST-41
A US federal framework streamlining permitting for projects of
national strategic importance.
✓ Improves transparency, predictability, and interagency
coordination
✓ Projects listed on the Federal Permitting Dashboard
✓ Promotes faster decisions, reduces delays
Why it matters for McDermitt:
• One of only 10 mining/resource projects initially designated
Project
Operator
Market Cap (US$M)
Resolution Copper
$101,260
Caldwell Canyon Mine
$27,573
Silver Peak Lithium
$6,560
Libby Project
$3,206
Warrior Met Coal Mines
$2,338
Stibnite Gold
$990
SW Akansas Lithium
$316
McDermitt Lithium
$21 M
Lisbon Valley Copper
Private
Michigan Potash
Private
• Underscores McDermitt’s role in US critical minerals strategy
• Reinforces confidence in permitting pathway and strategic
relevance
• Supports advancement of Exploration Plan of Operations
Sources:
• Market Capitalisation data from S&P CapIQ Pro 30 May 2025
• First 10 Transparency Projects sourced from here: Link
4
Company overview
Corporate snapshotC
Share price (ASX:JLL, OTCQX:JNDAF)
Share Capital (ASX:JLL, OTCQX:JNDAF)
76.9m
Share Price
A$0.42
Options from (40c to $5.00)
27.3m
Market Capitalisation
A$31.9m
CashD
A$3.7m
Investments
A$0.3m
Convertible Note
A$2.3m
Enterprise Value
A$30.2m
A$/share
1.20
1.00
0.80
0.60
Major shareholdersC
Lindsay Dudfield
22.9%
Kale Corporation
9.3%
Mercer Street
4.2%
Kevrex Pty Ltd
3.2%
Elmix Pty Ltd
2.9%
0.40
0.20
(C) As at 29 May 2025 unless noted otherwise; (D) Cash as at 31 March
2025
5
Investor Presentation
Who We Are
0.00
Jan-24
Feb-24
Mar-24
Apr-24
May-24
Jun-24
Jul-24
Aug-24
Sep-24
Oct-24
Nov-24
Dec-24
Jan-25
Feb-25
Mar-25
Apr-25
May-25
McDermitt is one of only four sedimentary lithium projects in the
US with Reserves (2.34Mt LCE1) but is trading at a fraction of
its peers, offering unmatched leverage to the upside.
Jindalee trades at an attractive
valuation relative to peers
Market Cap (US$)E / Contained LCEF in ResourcesH (t)
57.0
Market Cap (US$)E / Contained LCEF in ReservesH (t) 322.2
14.7
67.8
7.3
26.5
4.6
2.6
0.7
3.5
8.8
1.0
Nevada Lithium Jindalee Lithium Arizona Lithium
Surge Battery American Lithium Century Lithium Lithium Americas
Metals
Ioneer
Jindalee
Lithium
Century
Lithium
Lithium
Americas
Ioneer
Projects
Bonnie Claire
McDermitt
Big Sandy +
PraireI
Nevada
North
TLC +
FalchaniJ
Clayton
Valley
Thacker Pass
(62%)
Rhyolite
Ridge
Projects
McDermitt
Clayton Valley
Thacker Pass
(62%)
Rhyolite
Ridge
StageG
PEA
PFS
Scoping +
PFS
Pre-PEA
PEA +
PEA
FS
Construction
DFS
StageG
PFS
FS
Construction
DFS
Market Cap
(US$M)E
25
21
17
39
56
47
601
185
Market Cap
(US$M)E
21
47
601
185
(E) Jindalee Market Cap based an assumptions outlined on slide 4, converted to USD. All others sourced from S&P CapIQPro, 30 May 2025. (F) LCE = Lithium Carbonate
Equivalent. (G) Source: various company reports. (H) Refer Appendix 1 and 2 for further details including data sources and resource and reserve classification breakdown.
Resource and reserve estimates used on this slide have been adjusted to reflect equity ownership level. (I) Arizona Lithium holds two development projects: a) Big Sandy
Sediment Hosted project and b) Prairie Brine Direct Lithium Extraction project. (J) American Lithium holds two lithium development projects: a) Tonopah (TLC) Sediment hosted
project and b) Falchini hard rock deposit. Metrics do not include Macusani Uranium deposit.
Investor Presentation
6
Board and management team with proven
success in creating value for shareholders
7
Wayne Zekulich
Lindsay Dudfield
Paul Brown
Non-Executive Chair
Executive Director
Non-Executive Director
Mr Wayne Zekulich was appointed to the
Jindalee Board as Chair on 1 February
2024. Wayne is a Consultant and NonExecutive Director who has substantial
experience in advising, structuring and
financing transactions in the
infrastructure and resources sectors.
Wayne is currently Chair of ASX listed
gold miner Pantoro Limited (ASX:PNR).
Mr Lindsay Dudfield is a geologist with
over 40 years’ experience in multicommodity exploration. Lindsay has
been responsible for managing Jindalee
since inception, guiding the Company
through the advancement of several
projects across various commodities and
jurisdictions. He is also a Non-Executive
Director of several ASX listed mineral
exploration companies.
Mr Paul Brown has over 23 years’
experience in the mining industry, most
recently with Mineral Resources
(ASX:MIN) where he was Chief
Executive – Lithium. He has a strong
track record in project/studies
management and mine planning and
management. Paul is currently Chief
Executive Officer of Core Lithium Ltd
(ASX:CXO).
Darren Wates
Ian Rodger
Todd Clewett
Non-Executive Director
Chief Executive Officer
Senior Advisor – External
Affairs
Mr Darren Wates is a corporate lawyer
with extensive experience in equity
capital markets, M&A, resources, project
acquisitions / divestments and corporate.
Darren was significantly involved in the
development, joint venture partnering
and eventual sale of the Mt Marion
Lithium Project in roles with ASX listed
company Neometals Ltd (ASX:NMT).
Mr Ian Rodger is a mining executive with
over 15 years of experience in technical,
corporate finance, and project leadership
roles. He worked on two major greenfield
mine developments at Rio Tinto before
transitioning to corporate finance at RFC
Ambrian, where he held senior roles in
London and Sydney. As Project Director
at Oz Minerals, he helped advance West
Musgrave Nickel Copper Project, leading
into Oz Minerals’ A$9.6B acquisition by
BHP.
Investor Presentation
Who We Are
Mr Todd Clewett is a senior executive
with over 20 years’ experience in
government relations, external affairs,
and strategic communications across the
mining, energy, and infrastructure
sectors. He has held global leadership
roles with Newmont, Fortescue, First
Quantum, and Rio Tinto, leading external
engagement on major projects in the US,
LATAM, Africa, and Asia.
Empowering American
manufacturing and
energy security(1)
McDermitt is one of the largest lithium deposits in the US and of global significance. McDermitt is
ideally situated to plug in to the growing US battery manufacturing industry.
$3.23B(K)
17.9%
$3.02B
$8,080/t LCE(K,O)
Post Tax(L)
NPV (8%)
Post Tax(L)
IRR
CAPEX Inc.
$495M contingency
Bottom half
of cost curve(A)
47,500 tpa(M)
+40 Years(N)
5 Years
2.34 Mt LCE(O,P)
Lithium Carbonate
for first decade
Economic Evaluation Period,
total project life of 63 years
Project payback
from first production(1)
Ore Reserve
(~10% of Resource)
Robust returns
Perfect Timing
Made in the US
The Opportunity
Forecast EBITDA margins of +60%, generating post-tax
FCF of $6.6 B over the initial decade alone(L). Cash flows
resilient through price cycles with ~17% pre-tax net
operating cashflow margins (incl. sustaining capital) at
current spot prices.(Q)
Targeted permitting and development timeline sees first
Lithium Carbonate production aligning with forecast
substantial supply deficits in the early 2030s.(R)
Tax credits provide a powerful stimulus for domestic
production of lithium chemicals. Battery value chain
customers also incentivized to source domestically from
projects such as McDermitt.
McDermitt presents a rare opportunity for counter-cyclic
investors and partners looking to position in a commodity
poised for immense growth in the coming decade.
(K) All $ values in USD unless otherwise noted. (L) At $24,000/t lithium carbonate price, post tax values include estimated value of 45X tax incentives (refer to PFS Announcement). (M) First 10 years average post 12-month commissioning and ramp up. (N) PFS economic
evaluation period consists of construction, commissioning and ramp-up, followed by first 40 full years of production (Economic Evaluation Period). (O) Lithium Carbonate Equivalent, being the mass of lithium carbonate containing the same mass of lithium metal as the Ore
Reserve. Unit operating cost quoted on C1 basis. (P) Maiden Probable Ore Reserve (JORC 2012) (refer to PFS Announcement). (Q) US$10,866/t from Shanghai Metal Markets Lithium Carbonate Index (Battery Grade), delivered to China, VAT inclusive. As at 8 October
2024. (R) Benchmark Mineral Intelligence Q3 2024 dataset.
8
Investor Presentation
PFS Highlights
Stable mining
profile with early
access to ore(1)
● Mining will be by conventional truck and
shovel methods, with free-digging ore (no
blasting)
● Ore at surface limits pre-production mining /
stripping expense
● Mining stable at circa 20Mt p.a. and a life of
mine strip ratio of 1.3
● Accelerated mining schedule builds strategic
ore stockpiles:
○ An investment in production stability
○ Lower grade ores stockpiled for later
processing
9
Investor Presentation
PFS Highlights
Processing route validated
through testwork(1)
Our processing flowsheet consists of standard technology used
throughout industry and has been validated through testwork
supervised by Fluor Corporation.
McDermitt will be a fully integrated operation producing batterygrade Lithium Carbonate for sale to US customers.
Designed maximum annual production capacity of 47.5ktpa
Lithium Carbonate (limited by selected acid plant capacity).
Optimization opportunities will be studied under the recently
announced cooperative research agreement with the US
Department of Energy (DoE) including4:
• By-product potential
• Ore upgrading
• Water use optimization
10
Investor Presentation
PFS Highlights
Lithium supply crunch ahead
● Recent high prices (2022-23) led to a temporary supply surplus in global
lithium market
● Lithium prices have fallen to unsustainable levels, triggering
production cuts and project deferrals amid rising costs
○ Global lithium-ion battery demand surpassed 1 TWh for the first time
Kt LCE
1,100
800
EV sales rose 29% year-to-date to March 2025T, while Battery Energy
700
Storage System (BESS) deployments surged ~65% to ~34.3 GWh over
the same periodU
600
200
20,000
10,000
Jan 2025 price
Below $12/kg
5,000
100
0
What’s Our Market
+100%
-63%
400
● Major players are positioning for the rebound through JVs and acquisitions
(see slide 12)
(S) Source: Rho Motion link (T) Source: Rho Motion link (U) Source: Energy Storage News link (V) Source: SC insights link
25,000
500
300
Lithium’s next upcycle is coming — early investors will
capture the upside
Avg price over
2019-2023 was $30/kg
15,000
● Significantly higher prices are needed to incentivize new supply
Investor Presentation
30,000
900
in 2024S, growing 27% year-on-year—driven by strong uptake across
transport and stationary storage sectors.
● Market deficits are now expected earlier, with some analysts predicting
material shortfalls in 2026V
11
$/t Lithium
Carbonate
1,000
● Demand has continued to be robust:
○
Higher lithium prices required to meet future demand: Between
2019-2023, prices averaged ~$30/kg with ~515kt LCE supply added.
Today, spot prices are below $12/kg, yet demand forecasts
project ~1,000kt of additional supply required by 2028.
2019-2023
Source: SC Insights link
2024-2028F
Price (RHS)
New Supply
Added (LHS)
0
Market momentum for lithium continues
with JVs and credible, strategic partnerships
Development Funding
Increasing market activity by large players
Lithium Americas, Thacker Pass Project,
JV partners with General Motors
2025: Rio Tinto acquired Arcadium at 90% Premium
$6.7B
$945M
$250M
$2.26B
Total commitment from
General Motors
Funding provided via convertible note
and production payment agreement
with Orion Resource Parners LP
DOE loan
2025: Rio Tinto and Codelco form lithium JV in Chile
Up to $900M investment from Rio Tinto
Pre-Development Funding
2025: Pilbara Minerals acquired Latin Resources at
57% premium
12
Investor Presentation
2024
(Company –
Partner)
2023
(Company –
Partner)
2023
(Company –
Partner)
2024
(Company –
Partner)
2024
(Company –
Partner)
$160M
C$116M
$100M
C$25M
A$8M
Pathway Forward - Source data contained in Appendix 3.
Major milestones and catalysts for the year ahead
Q1 2025
Q2 2025
Q3 2025
2025
Appoint strategic advisors to assist with
partnership process
✔
Further work in 2025 to be considered in parallel
with partnership process:
Commence partnership engagement process
✔
Large infill exploration drilling program
Designated FAST-41 Transparency Project(3)
✔
Potential Department of Defense (DoD) grant application award (to co-fund next stage of work)(6)
Comprehensive metallurgical test work program
Commence Feasibility Study
Complete Exploration Plan of Operation (EPO) approvals for multi-year infill and exploration drilling program
13
Investor Presentation
Pathway Forward
(6): Refer to JLL ASX release 23/09/2024 “US Government Funding Update”.
Thank you
Further information
Ian Rodger
enquiry@jindaleelithium.com
Chief Executive Officer
+61 8 9321 7550
jindaleelithium.com
Vrify 3D Presentation
View in Vrify
15
Investor Presentation
Vrify 3D Presentation
McDermitt: A highly competitive source
of lithium chemicals for the US Market
● McDermitt to be in the bottom half of the global cost curve on LCE basis
● Aligned to US energy security goals, McDermitt is expected to provide a large,
long life domestic source of lithium chemicals at highly competitive C1
operating cost relative to North American peers:
North American Brines
North American Direct Lithium Extraction (DLE)
○ Comparable to North American DLE projects (mid-range)
North American Spodumene Integrated
○ At lower end of the range of forecasts for North American integrated
North American Spodumene Non-Integrated
spodumene producers
● Also cost competitive against Australian integrated spodumene producers
Australian Spodumene Integrated
● Lower cost supply (first quartile) is primarily from South American brine
operations
Rest of World (RoW) Production
Source: All Cost curve data from Benchmark Minerals Intelligence 2030 C1 cost curve Q3 2024 dataset (incl. cost, production and
project details). McDermitt is not included in cost curve and location is illustrated via text only, based on McDermitt PFS outputs
16
Investor Presentation
Supporting Data
McDermitt comparison with Thacker Pass
Joint Venture (62%/38%)
Category
McDermitt PFS (November 2024)IV,V
Thacker Pass (Updated Project Plan January 2025)I,II,III
EBITDA Margin
64%
65%
Operating Cash Cost
US$8,673/t
(Defined as C1 cash costs)
US$8,039/t
NPV8% (post tax)
US$3,229M
US$8,691M
IRR (post tax)
17.9%
20.0%
Development capital
US$3,021m (inclusive of US$495m contingency)
Phase 1: US$2,930m
LOM: US$12,327m
Average lithium Process Feed grade
1,967 ppm
2,538 ppm
Beneficiation separation size / course gangue rejects
125 microns
75 microns
Average lithium recovery
84.4%
80.4%
Average Lithium Carbonate production
43.8ktpa (47.5ktpa capacity)
Phase 1 Capacity: 40ktpa
135ktpa (max capacity 160ktpa)
Lithium price assumed
US$24,000/t
US$24,000/t
Project Life
63 years
85
Reserves and Resource
Reserves: 2.34 Mt of contained LCE @ 1,340ppm Li
Resource: 21.5 Mt of contained LCEVI @ 1,751ppm Li
Reserves: 14.3 Mt of contained LCE @ 3,180ppm Li
Resource: 66.1 Mt of contained LCEVI@ 2,175 ppm Li
Location
Oregon
Nevada
Engineering Consultants
Fluor Corporation and Cube Consulting
SGS, Sawtooth, NewFields, Bechtel and EXP
Other
Operational
Financial
Owners
Notes:
I.
Lithium Americas’ recent update outlines a phased expansion plan across five stages, targeting a total capacity of 160 ktpa of lithium carbonate.
II. Phase 1, currently under development, has a planned capacity of 40ktpa of lithium carbonate, requiring development capital of US$2,930m. The total development capital across all phases is US$12,327m.
III. Lithium Americas reports financial, cost, and production metrics based on the full expansion plan over different time horizons, incorporating all five phases, but does not provide standalone metrics for Phase 1.
IV. Jindalee’s PFS, by contrast, considers a single development stage with a capacity of 47.5ktpa of lithium carbonate and does not assume any staged expansions.
V. Financial, cost and production for McDermitt are over the project’s Economic Evaluation Period alone, not the full 63 year project life (PFS Economic Evaluation Period consists of construction, commissioning and ramp-up, followed by first 40 full years of production)
VI. Metrics included in table are quoted on life of project basis unless otherwise denoted.
VII. Inclusive of mineral reserves
Data Sources:
• McDermitt: McDermitt PFS released by Jindalee Lithium on 19 November 2024 (link) .
• Thacker Pass: Thacker Pass project update 7 January 2025 (link)
• Breakdown of Resources by category included in Appendix 2.
17
Investor Presentation
Supporting Data
Partnerships will continue
to move Jindalee along the
path to production
Jindalee’s PFS, led by Fluor Corporation and supported by Cube
Consulting, gives the Company confidence the Project is worth
pursuing further, as a huge resource with massive upside for
investors and partners.
✓ 2024 strategic research and development agreement with US DoE(4),
in collaboration with US universities and Oregon permitting agency
✓ Specialist US advisors to target government funding
✓
US Presence
Corporate advisors appointed to target strategic partners(5)
● US DoD grant application in progress for Feasibility Study* co-funding
● Deeper engagement with potential partners now PFS is complete
● Targeting partners with complementary skillsets
● Partner/s to provide input on and funding for Feasibility Study*
* including associated pre-development activities including infill drilling and metallurgical testwork
(5) Refer to JLL ASX release 31/03/2023 “Corporate Update”
18
Investor Presentation
Pathway Forward
Plugged Into the Battery Value Chain
Key PFS metrics
demonstrate encouraging
economic outcomes(1)
Dimensions
Lithium carbonate
price
$/t
Short-term and long-term opportunities for stakeholders
Lithium carbonate
produced
dry
tonnes
475,000
1,295,355
1,796,169
Gross revenue
$M
11,400
31,089
43,108
Construction
capital
$B
Payback period
Years
Sustaining capital
$M
Free cashflow
$M
C1 Costs*
$/t LCE
8,080
8,886
8,673
EBITDA
$M
7,562
19,578
27,530
EBITDA Margin
EBITDA/
Revenue
66%
63%
64%
NPV (8%)
$M
3,895
3,229
IRR
%
18.1%
17.9%
$750M
Unit
First 10 full years
Pre-tax
Post-tax
Next 30 years
Pre-tax
Post-tax
Economic evaluation
period
Pre-tax
Post-tax
24,000
3.02
average yearly EBITDA over first 10 years
47.5 kt
1,000 jobs
600 jobs
of lithium per year over
the first 10 years
during constuction
in operation
63-year
C1 costs
below
project life
current spot prices
66%
$3.2B
EBITDA margin in first
10 years
19
Post tax NPV
Investor Presentation
5 year
payback period from
production
17.9%
5
102
406
6,629
7,108
18,680
508
14,022
23,080
18,061
Post tax IRR
PFS Highlights
Opportunities to
further optimize with
untapped optionality
While the PFS is robust, Jindalee has its eye on key levers that
can further de-risk the Project through improvements to design,
cost and sustainability, for example:
● Process optimization
● Exploration and infill drilling
● Mining method optimization
● Extractin