McDermitt PFS Presentation
Released
Released
Announcement PDF
McDermitt Lithium Project
Preliminary Feasibility Study
Nov 2024
McDermitt Lithium Project
Preliminary Feasibility Study
(PFS)
Ian Rodger
Chief Executive Officer
ASX Code
QTCQX
JLL
JNDAF
jindaleelithium.com
This presentation summarises the results contained within JLL ASX release
19/11/2024 “McDermitt PFS - Multi-Decade Source of US Lithium Carbonate”
and should be read in conjunction with this announcement.
All dollars quoted in this Presentation are in US dollars unless otherwise noted.
Warning Statement
This Presentation has been prepared by Jindalee Lithium Limited (“Jindalee,”
“Company” or “JLL”) and is authorized for release by its Chief Executive Officer, Mr. Ian
Rodger. This presentation provides general background information about Jindalee’s
activities. That information is current at the date of this presentation and remains
subject to change without notice. Certain information in this presentation has been
derived from third parties and though Jindalee has no reason to believe that it is not
accurate, reliable, or complete, it has not been independently audited or verified by
Jindalee. Except to the extent required by law, Jindalee makes no representations or
warranty as to the accuracy, reliability, or completeness of information in this
document and does not take responsibility for updating any information or
correcting any errors or omissions which may become apparent after this
presentation is released.
This presentation is for information purposes only and is a summary and does not
purport to be complete nor does it contain all the information which would be
required in, nor is it, a prospectus, product disclosure statement, or other disclosure
document under Australian law or any other law (and will not be lodged with the
Australian Securities and Investments Commission or any foreign regulator) and is
not, and does not constitute, an invitation or offer of securities for subscription,
purchase, or sale in any jurisdiction. In particular, this presentation does not
constitute an invitation or offer of securities for subscription, purchase, or sale in the
United States or any other jurisdiction in which such an offer would be illegal. The
securities referred to in this presentation have not been and will not be registered
under the U.S. Securities Act of 1933 as amended or the securities laws of any state or
other jurisdiction of the United States and may not be offered or sold, directly or
indirectly in the United States.
Pre-Feasibility Study. The Pre-Feasibility Study, including the production target and
the forecast financial information derived from the production target, referred to in
this presentation (PFS) was first released to the ASX on 19 November 2024 (PFS
Announcement). This presentation includes summary excerpts from the PFS and
does not purport to be all-inclusive or complete and should be read together with the
PFS Announcement. The Company confirms that all material assumptions and
technical parameters underpinning the production target and the forecast financial
information derived from the production target, continue to apply and have not
materially changed.
All amounts are in US$ unless stated otherwise.
Shareholders and prospective investors should be aware that the PFS and this
presentation does not include any forecast financial information in respect of the
period after the initial 40 years of the Processing Schedule (post single commission
and ramp up year), as Jindalee cannot, at this stage, provide forecast financial
information for that subsequent period.
This presentation contains certain forward-looking statements, including forecast
financial information. Forward-looking statements include but are not limited to
statements concerning Jindalee’s current expectations, estimates, and projections
about the industry in which Jindalee operates and beliefs and assumptions regarding
Jindalee’s future performance. When used in this document, the words such as
“anticipate,” “could,” “plan,” “estimate,” “expects,” “seeks,” “intends,” “may,” “potential,”
“should,” and similar expressions are forward-looking statements. Although Jindalee
believes that that it has a reasonable basis for those forward looking statements and
forecast financial information, including the use of a flat US$24,000/t lithium
carbonate price in the PFS, the production target set out in this presentation and the
financial information based on it , such statements are subject to known and
unknown risks, uncertainties, and other factors, some of which are beyond the
control of Jindalee and no assurance can be given that actual results will be
consistent with these forward-looking statements. The basis for that conclusion is
contained throughout the PFS Announcement and all material assumptions,
including the JORC modifying factors, upon which the forward looking statements
and forecast financial information are based, are disclosed in the PFS Announcement
and this presentation should be read together with the PFS Announcement.
To achieve the range of outcomes indicated in the PFS, the PFS estimates that
funding in the order of $3.02B in construction capital will be required. Shareholders
and investors should be aware that there is no certainty that Jindalee will be able to
raise the required funding when needed and it is possible that such funding may only
be available on terms that may be highly dilutive or otherwise adversely affect
Jindalee shareholders’ exposure to the McDermitt Lithium Project (Project)
economics. Specifically, as outlined in the PFS Announcement, Jindalee intends to
pursue potential third party partnerships (with parties who have the potential to be
joint venture partners in the Project) to advance the Project and may pursue other
value realisation strategies such as a sale or partial sale of the Project or underlying
future commodity streams. If it does so, such arrangements may materially reduce
Jindalee’s proportionate ownership of the Project and/ or adversely affect Jindalee
shareholders’ exposure to the Project economics.
Statements in this presentation regarding the Company’s business, which are not
historical facts, are forward-looking statements that involve risks and uncertainties.
These include, among others, risks and uncertainties related to Mineral Resource and
Ore Reserve estimates, production targets, forecast financial information, lithium
carbonate prices, capital and operating costs, risks related to results of current or
planned exploration activities, changes in market conditions, obtaining appropriate
approvals to undertake exploration activities in the portfolio of projects, changes in
exploration programs and budgets based upon the results of exploration, future
prices of minerals resources; grade or recovery rates; accidents, labour disputes, and
other risks of the mining industry; delays in obtaining government approvals or
financing or in the completion of development or construction activities; movements
in the share price of investments and the timing and proceeds realized on future
disposals of investments, force majeure events, as well as those factors detailed in
the PFS Announcement or, from time to time, in the Company’s interim and annual
financial statements and reports, all of which are available for review on ASX at
asx.com.au and OTC Markets at otcmarkets.com.
Although the Company has attempted to identify important factors that could cause
actual actions, events or results to differ materially from those described in forwardlooking statements will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements. Accordingly,
readers should not place undue reliance on forward-looking statements. To the
extent permitted by law, Jindalee and its officers, employees, related bodies
corporate and agents disclaim all liability, direct, indirect or consequential (and
whether or not arising out of the negligence, default, or lack of care of Jindalee and/or
any of its agents) for any loss or damage suffered by a recipient or other persons out
of, or in connection with, any use or reliance on this presentation or information. This
presentation does not constitute investment advice and has been prepared without
taking into account any investor's particular investment objectives, financial
circumstances or particular needs and the opinions and recommendations in this
presentations are not intended to represent recommendations of particular
investments to particular persons. You should seek professional advice when
deciding if an investment is appropriate. All securities transactions involve risks,
which include (among others) the risk of adverse or unanticipated market, financial
or political developments.
Please refer to Appendix 5 for details of the Competent Persons Statement’s relating
to the Mineral Resources and Ore Reserves contained in this Presentation.
Empowering American
manufacturing and energy security
McDermitt is currently the largest lithium deposit in the US and of
global significance. McDermitt is ideally situated to plug in to the
growing US battery manufacturing industry.
$3.23 B(A)
17.9%
US$3.02 B
$8,080/t LCE(A,F)
Post Tax(B)
NPV8
Post Tax(B)
IRR
CAPEX
Inc. $495M contingency
Bottom half of
cost curve(E)
47,500 tpa(C)
+40 Years(D)
5 Years
Lithium Carbonate
for first decade
Economic Evaluation Period,
total project life of 63 years
Project payback
from first production(1)
2.34 Mt LCE(F,G)
Ore Reserve
(~10% of Resource)
(1) All information contained within JLL ASX release 19/11/2024 “McDermitt PFS - Multi-Decade Source of US Lithium Carbonate.” (PFS Announcement)
Robust returns
Forecast EBITDA margins of +60%, generating
post-tax FCF of $6.6B over the initial decade
alone (C). Cash flows resilient through price cycles
with ~17% pre-tax net operating cashflow
margins (incl. sustaining capital) at current spot
prices. (H)
Perfect Timing
Targeted permitting and development
timeline sees first Lithium Carbonate
production aligning with forecast substantial
supply deficits in the early 2030s. (I)
Made in the US
Tax credits provide a powerful stimulus for
domestic production of lithium chemicals.
Battery value chain customers also
incentivised to source domestically from
projects such as McDermitt.
The Opportunity
McDermitt presents a rare opportunity for
counter-cyclic investors and partners looking
to position in a commodity poised for
immense growth in the coming decade.
(A) All $ values in USD unless otherwise noted. (B) At $24,000/t lithium carbonate price, post tax values includes estimated value of 45X tax incentives (refer to PFS Announcement). (C) First 10 years average post 12-month commissioning and
ramp up. (D) PFS economic evaluation period consists of construction, commissioning & ramp-up, followed by first 40 full years of production (Economic Evaluation Period). (E) Benchmark Mineral Intelligence 2030 C1 Lithium Carbonate Equivalent
Cost Curve (Q2 2024 dataset). (F) Lithium Carbonate Equivalent, being the mass of lithium carbonate containing the same mass of lithium metal as the Ore Reserve. (G) Maiden Probable Ore Reserve (JORC 2012) (refer to PFS Announcement) (H)
US$10,866/t from Shanghai Metal Markets Lithium Carbonate Index (Battery Grade), delivered to China, VAT inclusive. As at 8 October 2024. (I) Benchmark Mineral Intelligence Q2 2024 dataset.
Who We Are
Fully integrated
operation to provide
battery feedstock to US
supply chains
Strong board and
management
ownership
Jindalee is dedicated to accelerating America’s
immense potential for a clean energy future.
The McDermitt Lithium Project on the Oregon-Nevada
border is the Company’s flagship project.
20 years worth of successful mineral
exploration and development
+
The Project’s attributes align with US strategic policy of
critical mineral independence through domestic
production of Lithium Carbonate.
The PFS marks a key turning point for this companymaking project, demonstrating a robust project with
potential to materially contribute to the energy future
of the US.
Proven success in creating value
for shareholders
6
McDermitt Lithium PFS Presentation
Who We Are
7
2018
2020
2022
2024
Jindalee stakes McDermitt Lithium
Project; drills 4 "proof of concept"
holes which confirm size potential
of McDermitt.
Encouraging results from
metallurgical testwork, another 1
holes drilled.
Spin-out of Australian assets as
Dynamic Metals (ASX:DYM) to
focus on McDermitt. Resource
increases to 13.3 Mt LCE,
environmental baseline studies
commence & 21 more holes drilled.
Excellent metallurgical results, with
battery grade Lithium Carbonate
produced. Strategic research
agreement with DOE signed.
Results of PFS announced.
5
2019
2021
2023
Completes more drilling, Jindalee
announces maiden resource (1.6
Mt LCE).
McDermitt resource increases to
10.1MT LCE, 12 more holes drilled.
Resource increases to 21.5Mt LCE ,
MOU signed with POSCO & PFS
commences. Ian Rodger appointed
CEO & Wayne Zekulich as Chair.
McDermitt Lithium PFS Presentation
Who We Are
A remarkable opportunity
connected to the American
battery value chain
In 2023, drilling increased McDermitt to
21.5Mt LCE, the largest lithium deposit in the
US and a company-making Project(2).
Project overview
McDermitt Caldera is on the Oregon-Nevada border
Ideal proximity to roads, rail, power and civil infrastructure
+40 year project life
Attracted interest of POSCO Holdings (POSCO)(3), a major
supplier and partner to General Motors in North America
First production target aligns with significant forecast
supply deficits in early 2030s
Strategic agreement with US Department of Energy (DoE)(4),
and in the mix for feasibility co-funding via grant with US
Department of Defense (DoD)(5)
(2): JLL ASX release 27/02/2023 “Resource at McDermitt increases to 21.5 Mt LCE" (3): Refer to
JLL ASX release 13/02/2023 “MOU Executed with POSCO Holdings” (4): Refer to JLL ASX release
16/09/2024 “Jindalee Secures Strategic Agreement with US Department of Energy” (5): Refer to
JLL ASX release 23/09/2024 “US Government Funding Update”.
8
McDermitt Lithium PFS Presentation
Who We Are
Project tenure spans
Contained resource(2)
21.5Mt LCE
13,606 acres
(55km2)
35km west
from McDermitt township
PFS Technical
Overview
We’re making progress to
help the US achieve critical
mineral independence
Our PFS, led by Fluor Corporation and
supported by Cube Consulting, demonstrates
compelling economics justifying the next phase
of study; a huge resource with massive upside
for investors and partners.
Key takeaways
Next steps
Cost competitive Li over 40+ years
Exploration Plan of Operation (EPO) approval
Strong economic returns
Further baseline studies and community engagement
Simple, low-cost mining operation
Continue work under Cooperative Research and
Development Agreement (CRADA) with US DoE(4)
Flowsheet validated via metallurgical testwork
Process consists of standard technologies used
across industry
Proven battery grade Lithium Carbonate product
10
McDermitt Lithium PFS Presentation
PFS Technical Overview
Infill drilling campaign
Metallurgical testwork
Feasibility Study
Resources & Reserves
Limited Resource Conversion (current state)
Maiden Ore Reserve announced with the PFS results
Reserve is only ~10% of the Resource, presenting a
significant upside opportunity
63 year project life underpinned by 79% Probable
Reserves, 3% Indicated and 18% Inferred.
Mineral Resource Estimate (2)
Classification
Tonnage (Mt)
Li Grade (ppm)
Contained LCE (Mt)
Indicated Resource
1,470
1,420
11.1
Inferred Resource
1,540
1,270
10.4
Total Resource
3,000
1,340
21.5
Note: Reporting cut-off grade of 1,000 ppm lithium. Totals may vary due to rounding
First 20 years contain only 5% Inferred
McDermitt has the largest LCE Resource currently
defined in the US
Permitting underway for 2025 infill drilling program
focused on resource/reserve upgrade
McDermitt Lithium Project Open Pit Ore Reserves Estimate (1)
Category
Ore Tonnes (Mt)
Li Grade (ppm Li)
Contained LCE (Mt)
Probable
251
1,751
2.34
Note: (1) Cut-off grade of 1,000 ppm Li applied. (2) Run of Mine Processed grade.
Probable Reserve
Exploration Opportunity
Indicated Resource
Million tonnes
25
20
10.4
15
10
11.1
5
2.34
0
Probable Reserve
11
McDermitt Lithium PFS Presentation
PFS Technical Overview
Mineral Resource
Inferred Resource
Stable mining
profile with early
(1)
access to ore
25
Mining Movements (Mt)
20
Mining will be by conventional truck and
shovel methods, with a free-digging ore
body (no blasting)
15
10
5
0
1
Ore at surface limits pre-production mining /
6
11
16
21
26
31
36
Years
stripping expense
Waste
Mining stable at circa 20Mt p.a. and a life of
Ore
mine strip ratio of 1.3
Accelerated mining schedule builds
strategic ore stockpiles:
B
B’
Grade Li (ppm)
An investment in production stability
Proposed Pit Shell
>2000
1500-2000
1000-1500
Lower grade ores stockpiled for later
Proposed Pit Shell
processing
1600m RL
Unit 10
Unit 8
Unit 6
Unit 4
0
1000m
Vertical exaggeration: 3x
12
McDermitt Lithium PFS Presentation
PFS
Technical Overview
Processing route validated
through testwork
Coarse gangue
~28% mass rejection
ROM Ore
Our processing flowsheet consists of standard technology
used throughout industry, and has been validated through
testwork by Fluor.
Leach Feed
Attrition
Scrubbing
Acid Leaching,
Neutralisation
~4.8Mtpa of
ore feed
~3.5Mtpa feed
~72% mass recovery
~92% Li recovery
McDermitt will be a fully integrated operation producing
battery-grade Lithium Carbonate for sale to US
customers.
Designed maximum annual production capacity of
47.5ktpa Lithium Carbonate (limited by selected acid plant
capacity).
Ion Exchange,
Li Crystallisation
Optimisation opportunities will be studied under the
recently announced cooperative research agreement with
the US DoE including:
By-product potential
Ore upgrading
Water use optimisation
Tailings Storage
Li Solution
Li Solution
Mg & Ca
Removal
Li2CO3
Final Product
Battery grade
Li2CO3
Drying,
Packing
47.5ktpa of product
Total Recovery ~85%
Process Streams
Process Steps
Waste Streams
Note: Figures quoted reflect averages over first 10 years of commercial production
13
McDermitt Lithium PFS Presentation
PFS Technical Overview
Mg and Ca
removal
Huge asset, high-potential
Smoothed Annual Lithium Carbonate Production
Production forecasts show three distinct periods
50
Highest grade ores are prioritised for early treatment, giving an
initial 10 years producing 47.5ktpa of Lithium Carbonate, and a
further 30 years producing over 43ktpa average.
Intermediate grade ores stockpiled for the future - optimising
cash flows while providing an internal “insurance policy” against
production interruptions.
In the PFS, the lowest grade ores are processed after year 41,
when the current mining schedule ends.
his mining and processing strategy provides operational
fle ibility to the ompany, and maintains optionality to either
pand the processing capacity to accelerate production, or
ontinue displacing the lowest grade ores through
progressive esource conversion.
T
x
C
:
Ex
C
R
PFS conomic valuation Period only includes first 4 years of
production following commissioning and ramp up.
E
14
E
McDermitt Lithium PFS Presentation
40
thousand tonnes per annum
Drives fast five year payback.
45
35
30
25
Outside of Economic Evaluation Period
20
15
10
5
0
1
10
20
30
40
0
PFS Technical Overview
production year
50
60
70
Pre-production Capital
Estimate
Area
Long life process and refining facility drives
capital estimate
Process Plant
cDermitt’s integrated Lithium Carbonate refinery is
the majority of the $3.02B capital estimate prepared by
Fluor
M
Less than 5% of the capital estimate is based upon
allowances
inimal pre-production mining costs as outcropping
ore at surface
Estimate ($M)
1,042
Acid Plant
517
Non-Process Infrastructure
358
Engineering, Procurement and
Construction Management (EPCM)
273
Construction & Commissioning
164
Subtotal
2,354
Contingency
495
Mining (pre-strip)
23
Owners Costs
149
Total
3,021
M
ontingency of $495m was estimated by Fluor for a
70% confidence level - ie. at this level of contingency,
there is a 70% chance actual contingency spend will be
at or below this level
C
3
year construction period forecast
*May not total due to rounding
15
McDermitt Lithium PFS Presentation
PFS Technical Overview
Sustainable and profitable
through the commodity cycles
Short-term payback, long-term cash flows
Low cost, free dig mining averaging ~$3.50/t of material
moved (combined ore and waste)
Processing costs are circa $280m p.a., with reagents the
largest single cost area
Acid production represents ~35% of total operating costs,
but also generates ~80% of site-wide power requirement as
a “by-product”
At current spot prices(H), the Project would generate 17%
pre-tax net operating cashflow margins (including
sustaining capital costs) in the first 10 full years
Robust economics and short five year payback mean
McDermitt is well placed to capture the peaks of any price
cycles, while weathering the lows
First 10 full years1
Area
Next 30 Years
Project
Share
$M p.a.
$/t LCE
$/t LCE
94
1,970
1,905
21%
Regeants and
Consumables
219
4,605
4,946
73%
Labour and
Maintenance
Supplies
65
1,375
1,513
Utilities
13
266
330
Product
transport,
Camp
operations,
G&A
26
542
586
6%
Cash Operating Cost
416
8,759
9,281
100%
Inventory Movement2
(32)
(680)
(395)
C1 Cost
384
8,080
8,886
Mining and
rehandle
Process
Plant
Other
Excludes ramp-up yea
Inventory movement accounts for the progressive build up and draw down of ore stockpiles over time, to more accurately reflect mining
costs for lithium carbonate production in each period
16
McDermitt Lithium PFS Presentation
PFS Technical Overview
Vrify 3D
Presentation
View in Vrify
Project Economics
Key PFS metrics demonstrate
encouraging economic outcomes
Dimension
Units
First 10 full years
Pre-tax
Post-tax
Next 30 years
Pre-tax
Post-tax
Economic eval. period
Pre-tax
Post-tax
Lithium
carbonate
price
$/t
Lithium
carbonate
produced
dry
tonnes
475,000
1,295,355
1,796,169
Gross
revenue
$M
11,400
31,089
43,108
average EBITDA over first 10 years
Construction
capital
$B
47.5 kt
Payback
period
Years
Sustaining
capital
$M
Free
cashflow
$M
C1 Costs*
$/t LCE
8,080
8,886
8,673
EBITDA
$M
7,562
19,578
27,530
EBITDA
Margin
EBITDA/
Revenue
66%
63%
64%
NPV (8%)
$M
3,895
3,229
IRR
%
18.1%
17.9%
Short-term and long-term opportunities for investors
$750M
of lithium per year
over the first 10 years
63-year
project life
66%
1000 jobs
during constuction
C1 costs
below
current spot prices
EBITDA margin in first
10 years
$3.2B
Post tax NPV
600 jobs
in operation
5 year
payback period from
production
17.9%
24,000
3.02
5
102
7,108
406
6,629
18,680
508
14,022
23,080
18,061
*C1 cost includes operating costs for mining, processing, administration and product sales, after accounting for movements in inventory
related to ore stockpiles. It does not include 45X tax credits related to input costs (refer to PFS Announcement)
IRR
Economic Evaluation Period consists of construction, commissioning and ramp-up, followed by the first 40 full years of production.
18
McDermitt Lithium PFS Presentation
Project Economics
Sensitivity
Sensitivity Analysis
Pre Tax Free Cash Flow Sensitivity (±25%)
Three key sensitivities tested:
Revenue
Most sensitive, showing the potential impact of
changes in lithium carbonate prices. Typical for most
resource projects
Opex
Moderate sensitivity, with a 25% overrun on operating
costs reducing pre-tax NPV by circa $800m
Lithium
Carbonate Price
Recovery
(10% Test)
Opex
capex
10,000
14,000
Capex
Given the long life nature of McDermitt, project
returns show the least sensitivity to the initial project
capital cost
18,000
22,000
26,000
30,000
34,000
6,000
7,000
USD Million
Pre Tax NPV8 Sensitivity (±25%)
Lithium
Carbonate Price
Recovery
(10% Test)
Opex
capex
1,000
2,000
3,000
4,000
USD Million
19
McDermitt Lithium PFS Presentation
Project Economics
5,000
Opportunities to
further optimise with
untapped optionality
Largest LCE Resource in US/North America
3500
mcdermitT
Resources (Mt)
3000
While the PFS is robust, we have our eye on key
levers that can further de-risk the Project through
improvements to design, cost and sustainability, for
example:
2500
thacker pass
2000
clayton valley
1500
nevada north
1000
sonora
tlc
rhyolite ridge
500
big sandy
0
0
500
1000
1500
2000
2500
3000
3500
Resources Lithium Grade (ppm)
Sources contained Appendix 2, bubble size based on contained LCE
20
Process optimisation
Exploration and infill drilling
Mining method optimisation
Extracting/refining co-products
Optimising attrition, leaching
and recovery processes to
improve cost and sustainability
outcomes. Opportunities
include further upgrading ore
prior to leaching to reduce acid
consumption.
With less than 11% of contained
lithium currently converted to
Ore Reserve, infill drilling aims to
boost grade continuity
confidence and may identify
higher-grade zones for
prioritised processing.
Further investigation around
mining methods, designs and
scheduling have the potential to
reduce costs and minimise
disturbance.
Magnesium and other minerals
within the deposit may offer a
supplementary cash flow,
subject to further exploration,
metallurgical testing and
feasibility studies.
McDermitt Lithium PFS Presentation
Project Economics
Sustainability innovations
Further advancing
environmental sustainability
pathways, including reducing
water usage, by leveraging
strategic agreement with the
DoE, regional universities, and
the Oregon permitting agency(4).
Our pathway to
production is clear
21
McDermitt Lithium PFS Presentation
Project Economics
A clear roadmap for
the required approvals
Federal Agencies and Approvals
Federal Agency
Permit / Approval
Bureau of Land Management (BLM)
Mining Plan of Operations
National Environmental Policy Act (NEPA) - Record of Decision
Jindalee has appointed a US-based ESG Manager and will
conduct an ESG materiality assessment in H1 2025.
This assessment will help define specific ESG objectives and
inform the development of our longer-term ESG roadmap,
aligned with recognised international standards.
From 2022
Jindalee has conducted extensive environmental baseline
studies, cultural assessments and test work at the McDermitt
Project as part of exploration permitting and related activities.
In 2023
The Company completed a Social Risk Assessment and is
currently updating this as part of ongoing efforts to enhance
ESG outcomes.
In 2024
Continued baseline studies, accelerated community
engagement and executed tribal agreements and progressed
Exploration Plan of Operations.
Army Corps of Engineers
Clean Water Act, section 404 Permit (Waters of the United States)
US Fish and Wildlife Service (USFWS)
Disturbance Take Permit - Bald and Golden Eagle Protection Act
Incidental Take Permit - Endangered Species Act
Various federal and state agencies
Hazardous waste generation and repository permits
Oregon Agencies and Approvals
Oregon Agency
Permit / Approval
Oregon Department of Geology and Mineral
Industries (DOGAMI)
Consolidated Permit Approval (CPA)
Oregon Department of Water Resources (ODWR)
Water Rights
Diversion Dam Permit
Reservoir Permit
Dam Safety Permit
Oregon Health Authority (OHA)
Drinking Water Permit
Oregon department of Environmental Quality
(ODEQ)
Water Pollution Permits
Air Pollution Permits
Discharge Permit
Dewatering Permits
County Approvals
County (State)
Permit / Approval
Malheur (OR)
Land Use Compatibility Statement
Sage Grouse (GRSG) Permit
22
McDermitt Lithium PFS Presentation
Pathway Forward
Activity
Orange bars indicate current critical path
Partnerships
Baseline Studies
NEPA Permitting/
Record of Decision
Infill Drilling
2029
Pilot Test Work
Feasibility Study
FEED
Project Funding
Final Investment Decision
2029
Construction/
Commissioning
2032
Operations
2025
23
McDermitt Lithium PFS Presentation
Pathway Forward
Market momentum for lithium continues
with JVs and credible, strategic partnerships
Increasing market activity by large players
Development Funding
Rio Tinto to acquire Arcadium at 90% Premium
$6.7B
$945M
DOE loan
$700M
$650M
Total commitment from
Sibanye Stillwater
DOE loan
Pre-Development Funding
57% premium
McDermitt Lithium PFS Presentation
$2.26B
Total commitment from
General Motors
Pilbara Minerals to acquire Latin Resources at
24
ioneer, Rhyolite Ridge Project,
partners with Sibanye
Stillwater
Lithium Americas, Thacker Pass Project,
partners with General Motors
2024
(Company - Partner)
2023
(Company - Partner)
2023
(Company - Partner)
2024
(Company - Partner)
2024
(Company - Partner)
$160M
C$116M
$100M
C$25M
A$8M
Pathway Forward - Source data contained in Appendix 3.
Corporations and government
agencies are striving to develop
the US battery value chain
We are in a global race to compete in a
We will require all essential materials for our
future where electric propulsion will
national security to be produced here in the
undoubtedly be a giant force in
United States, creating millions and millions of
transportation.
new manufacturing jobs.
Ford Motor Company
President-elect Donald J Trump
(source: address to New York Economic Club on 5 September 2024)
Partnerships will continue
to move us along the path to
production
Partnerships Criteria
PFS, led by Fluor and supported by Cube, gives us
confidence the Project is worth pursuing further, as
Share your feedback