Investor Presentation
Released
Released
Announcement PDF
Investor Presentation
Dec 2024
McDermitt Lithium Project
Investor Presentation
Ian Rodger
Chief Executive Officer
ASX Code
QTCQX
JLL
JNDAF
jindaleelithium.com
This presentation summarises the results contained within JLL ASX release
19/11/2024 “McDermitt PFS - Multi-Decade Source of US Lithium Carbonate”
and should be read in conjunction with this announcement.
All dollars quoted in this Presentation are in US dollars unless otherwise noted.
Warning Statement
This Presentation has been prepared by Jindalee Lithium Limited (“Jindalee,”
Shareholders and prospective investors should be aware that the PFS and this
Statements in this presentation regarding the Company’s business, which are not
“Company” or “JLL”) and is authorized for release by its Chief Executive Officer, Mr. Ian
presentation does not include any forecast financial information in respect of the
historical facts, are forward-looking statements that involve risks and uncertainties.
Rodger. This presentation provides general background information about Jindalee’s
period after the initial 40 years of the Processing Schedule (post single commission
These include, among others, risks and uncertainties related to Mineral Resource and
activities. That information is current at the date of this presentation and remains
and ramp up year), as Jindalee cannot, at this stage, provide forecast financial
Ore Reserve estimates, production targets, forecast financial information, lithium
subject to change without notice. Certain information in this presentation has been
information for that subsequent period.
carbonate prices, capital and operating costs, risks related to results of current or
derived from third parties and though Jindalee has no reason to believe that it is not
accurate, reliable, or complete, it has not been independently audited or verified by
Jindalee. Except to the extent required by law, Jindalee makes no representations or
warranty as to the accuracy, reliability, or completeness of information in this
document and does not take responsibility for updating any information or
correcting any errors or omissions which may become apparent after this
presentation is released.
planned exploration activities, changes in market conditions, obtaining appropriate
This presentation contains certain forward-looking statements, including forecast
financial information. Forward-looking statements include but are not limited to
statements concerning Jindalee’s current expectations, estimates, and projections
about the industry in which Jindalee operates and beliefs and assumptions regarding
Jindalee’s future performance. When used in this document, the words such as
“anticipate,” “could,” “plan,” “estimate,” “expects,” “seeks,” “intends,” “may,” “potential,”
“should,” and similar expressions are forward-looking statements. Although Jindalee
approvals to undertake exploration activities in the portfolio of projects, changes in
exploration programs and budgets based upon the results of exploration, future
prices of minerals resources; grade or recovery rates; accidents, labour disputes, and
other risks of the mining industry; delays in obtaining government approvals or
financing or in the completion of development or construction activities; movements
in the share price of investments and the timing and proceeds realized on future
disposals of investments, force majeure events, as well as those factors detailed in
the PFS Announcement or, from time to time, in the Company’s interim and annual
This presentation is for information purposes only and is a summary and does not
believes that that it has a reasonable basis for those forward looking statements and
purport to be complete nor does it contain all the information which would be
forecast financial information, including the use of a flat US$24,000/t lithium
required in, nor is it, a prospectus, product disclosure statement, or other disclosure
carbonate price in the PFS, the production target set out in this presentation and the
document under Australian law or any other law (and will not be lodged with the
financial information based on it , such statements are subject to known and
Australian Securities and Investments Commission or any foreign regulator) and is
unknown risks, uncertainties, and other factors, some of which are beyond the
Although the Company has attempted to identify important factors that could cause
not, and does not constitute, an invitation or offer of securities for subscription,
control of Jindalee and no assurance can be given that actual results will be
actual actions, events or results to differ materially from those described in forward-
purchase, or sale in any jurisdiction. In particular, this presentation does not
consistent with these forward-looking statements. The basis for that conclusion is
looking statements will prove to be accurate, as actual results and future events
constitute an invitation or offer of securities for subscription, purchase, or sale in the
contained throughout the PFS Announcement and all material assumptions,
could differ materially from those anticipated in such statements. Accordingly,
United States or any other jurisdiction in which such an offer would be illegal. The
including the JORC modifying factors, upon which the forward looking statements
readers should not place undue reliance on forward-looking statements. To the
securities referred to in this presentation have not been and will not be registered
and forecast financial information are based, are disclosed in the PFS Announcement
extent permitted by law, Jindalee and its officers, employees, related bodies
and this presentation should be read together with the PFS Announcement.
corporate and agents disclaim all liability, direct, indirect or consequential (and
under the U.S. Securities Act of 1933 as amended or the securities laws of any state or
To achieve the range of outcomes indicated in the PFS, the PFS estimates that
funding in the order of $3.02B in construction capital will be required. Shareholders
Pre-Feasibility Study. The Pre-Feasibility Study, including the production target and
and investors should be aware that there is no certainty that Jindalee will be able to
the forecast financial information derived from the production target, referred to in
raise the required funding when needed and it is possible that such funding may only
this presentation (PFS) was first released to the ASX on 19 November 2024 (PFS
be available on terms that may be highly dilutive or otherwise adversely affect
Announcement). This presentation includes summary excerpts from the PFS and
Jindalee shareholders’ exposure to the McDermitt Lithium Project (Project)
does not purport to be all-inclusive or complete and should be read together with the
economics. Specifically, as outlined in the PFS Announcement, Jindalee intends to
PFS Announcement. The Company confirms that all material assumptions and
pursue potential third party partnerships (with parties who have the potential to be
technical parameters underpinning the production target and the forecast financial
joint venture partners in the Project) to advance the Project and may pursue other
information derived from the production target, continue to apply and have not
value realisation strategies such as a sale or partial sale of the Project or underlying
materially changed.
future commodity streams. If it does so, such arrangements may materially reduce
All amounts are in US$ unless stated otherwise.
asx.com.au and OTC Markets at otcmarkets.com.
whether or not arising out of the negligence, default, or lack of care of Jindalee and/or
other jurisdiction of the United States and may not be offered or sold, directly or
indirectly in the United States.
financial statements and reports, all of which are available for review on ASX at
any of its agents) for any loss or damage suffered by a recipient or other persons out
of, or in connection with, any use or reliance on this presentation or information. This
presentation does not constitute investment advice and has been prepared without
taking into account any investor's particular investment objectives, financial
circumstances or particular needs and the opinions and recommendations in this
presentations are not intended to represent recommendations of particular
investments to particular persons. You should seek professional advice when
deciding if an investment is appropriate. All securities transactions involve risks,
which include (among others) the risk of adverse or unanticipated market, financial
or political developments.
Jindalee’s proportionate ownership of the Project and/ or adversely affect Jindalee
Please refer to Appendix 5 for details of the Competent Persons Statement’s relating
shareholders’ exposure to the Project economics.
to the Mineral Resources and Ore Reserves contained in this Presentation.
Pure play US lithium company
focused on giant McDermitt Project
Oregon
View in Vrify
Key investment highlights:
Largest Lithium Resource in the US
Positioned as a significant asset in meeting America’s critical mineral needs.
Robust PFS Demonstrating Exceptional Economics (1)
Long-life, large-scale production of battery-grade lithium carbonate in the
bottom half of the industry cost curve.
(A)
i
L
Strategically Positioned to Address Medium-Term Supply Deficit
orecasted supply deficits from 2028 highlight McDermitt’s critical role in
supporting long-term lithium demand.
F
Thacker Pass Project
19.1Mt LCE (B)
Strong U.S. Government Engagement and Support
Nevada
Eligible for key tax credits, grants, and concessional loans. Currently
partnering with the US Department of Energy under Cooperative Research
and Development Agreement.
(3)
21.5Mt LCE
63 year
66%
Project life
EBITDA margin over the
first 10 years.
Transformative Year Ahead
Catalysing value with potential US government grant funding, strategic
partnerships, and permitting milestones.
(1) All information contained within JLL ASX release 19/11/2024 “McDermitt PFS - Multi-Decade
Source of US Lithium Carbonate.” (PFS Announcement) (2): JLL ASX release 27/02/2023 “Resource
at McDermitt increases to 21.5 Mt LCE” (3): Refer to JLL ASX release 16/09/2024 “Jindalee
Secures Strategic Agreement with US Department of Energy”
(A) Benchmark Mineral Intelligence 2030 C1 Lithium Carbonate Equivalent Cost Curve (Q3 2024 dataset). (B) See appendix 1
for source and detailed breakdown of resource estimate
Contained resource(2)
Company overview
Corporate snapshot1
Share
Capital
Share
Price
Options
Market
(ASX:JLL,
Share price (ASX:JLL, OTCQX:JNDAF)
OTCQX:JNDAF)
73.6m
/share
A$
A$0.24
from
(40c
to
$5.00)
Capitalisation
25.8m
A$17.7m
Cash2
A$3.4m
Investments
A$2.7m
1.25
1.00
Convertible
Enterprise
Note
A$2.8m
Value
A$11.3m
0.75
Major Shareholders1
0.50
Lindsay
Kale
Dudfield
23.6%
Corporation
Mercer
8.9%
Street
0.25
4.1%
o
0.0
Kevrex
Elmix
Pty
Pty
Ltd
3.4%
Ltd
-0.25
3.0%
(1) As at 25 November 2024 unless noted otherwise; (2) Cash as at 30 September
2024
5
Investor Presentation
Who We Are
Board and management team with proven
success in creating value for shareholders
Wayne Zekulich
Lindsay Dudfield
Paul Brown
Non-Executive Chair
Executive Director
Non-Executive Director
Mr Wayne Zekulich was appointed to
Mr Lindsay Dudfield is a geologist
Mr Paul Brown has over 23 years’
the Jindalee Board as Chair on 1
with over 40 years’ experience in
experience in the mining industry,
February 2024. Wayne is a Consultant
multi-commodity exploration. Lindsay
most recently with Mineral Resources
and Non-Executive Director who has
has been responsible for managing
(ASX:MIN) where he was Chief
substantial experience in advising,
Jindalee since inception, guiding the
Executive – Lithium. He has a strong
structuring and financing transactions
Company through the advancement
track record in project/studies
in the infrastructure and resources
of several projects across various
management and mine planning and
sectors. Wayne is currently Chair of
commodities and jurisdictions. He is
management. Paul is currently Chief
ASX listed gold miner Pantoro Limited
also a Non-Executive Director of
Executive Officer of Core Lithium Ltd
(ASX:PNR).
several ASX listed mineral exploration
(ASX:CXO).
companies.
Darren Wates
Ian Rodger
Brett Marsh
Non-Executive Director
Chief Executive Officer
VP Exploration and
Development
6
Mr Darren Wates is a corporate lawyer
Mr Ian Rodger is the newly appointed
with extensive experience in equity
CEO of Jindalee. Ian is an
Mr Brett Marsh is a Geologist with
capital markets, M&A, resources,
internationally experienced mining
over 25 years of experience. He has
project acquisitions / divestments and
executive, with experience as a mining
managed all phases of the mining
corporate. Darren was significantly
engineer working across two large
lifecycle including greenfield and
involved in the development, joint
greenfield mine developments with
brownfield exploration, project
venture partnering and eventual sale
Rio Tinto. He also has a broad range of
development (including preliminary
of the Mt Marion Lithium Project in
corporate finance and commercial
economic assessments, pre-
roles with ASX listed company
experience, holding senior roles at
feasibility and feasibility), project
Neometals Ltd (ASX:NMT).
RFC Ambrian, BHP and Oz Minerals
construction, mine operations, and
(ASX:OZL).
environmental.
Investor Presentation
Who We Are
Empowering American
(1)
manufacturing and energy security
$3.23 B
17.9%
(C)
(D)
growing US battery manufacturing industry.
CAPEX
+40 Years
(A)
cost curve
ears
(F)
(C,G)
Bottom half of
Inc. $495M contingency
IRR
(E)
$8,080/t LCE
US$3.02 B
Post Tax
NPV (8%)
7,500 tpa
global significance. McDermitt is ideally situated to plug in to the
(D)
Post Tax
4
McDermitt is currently the largest lithium deposit in the US and of
2.34 Mt LCE
(G,H)
5 Y
Lithium Carbonate
Economic Evaluation Period, total
Project payback
Ore Reserve
for first decade
project life of 63 years
from first production
(~10% of Resource)
(1)
Robust returns
Perfect Timing
Made in the US
T
Forecast EBITDA margins of +60%, generating
Targeted permitting and development timeline
Tax credits provide a powerful stimulus for
McDermitt presents a rare opportunity for
post-tax FCF of $6.6B over the initial decade
sees first Lithium Carbonate production aligning
domestic production of lithium chemicals.
counter-cyclic investors and partners looking to
alone (D). Cash flows resilient through price cycles
with forecast substantial supply deficits in the
Battery value chain customers also incentivised
position in a commodity poised for immense
with ~17% pre-tax net operating cashflow
early 2030s. (J)
to source domestically from projects such as
growth in the coming decade.
margins (incl. sustaining capital) at current spot
he Opportunity
McDermitt.
prices. (I)
(C) All $ values in USD unless otherwise noted. (D) At $24,000/t lithium carbonate price, post tax values includes estimated value of 45X tax incentives (refer to PFS Announcement). (E) First 10 years average post 12-month commissioning and ramp up. (F) PFS economic evaluation period consists of
construction, commissioning & ramp-up, followed by first 40 full years of production (Economic Evaluation Period). (G) Lithium Carbonate Equivalent, being the mass of lithium carbonate containing the same mass of lithium metal as the Ore Reserve. Unit operating cost quoted on C1 basis. (H) Maiden
Probable Ore Reserve (JORC 2012) (refer to PFS Announcement) (I) US$10,866/t from Shanghai Metal Markets Lithium Carbonate Index (Battery Grade), delivered to China, VAT inclusive. As at 8 October 2024. (J) Benchmark Mineral Intelligence Q3 2024 dataset.
7
Investor Presentation
PFS Highlights
Stable mining
profile with early
(1)
access to ore
25
Mining Movements (Mt)
20
Mining will be by conventional truck and
shovel methods, with a free-digging ore
body (no blasting)
15
10
5
0
1
Ore at surface limits pre-production mining /
6
11
16
21
26
31
36
Years
stripping expense
Waste
Mining stable at circa 20Mt p.a. and a life of
Ore
mine strip ratio of 1.3
Accelerated mining schedule builds
B
strategic ore stockpiles:
B’
Grade Li (ppm)
An investment in production stability
Proposed Pit Shell
Lower grade ores stockpiled for later
>2000
1500-2000
1000-1500
processing
Proposed Pit Shell
1600m RL
Unit 10
Unit 8
Unit 6
Unit 4
0
1000m
Vertical exaggeration: 3x
8
Investor Presentation
PFS Highlights
Processing route validated
(1)
through testwork
Coarse
~28%
mass
gangue
ROM Ore
Our processing flowsheet consists of standard technology
used throughout industry, and has been validated through
testwork supervised by Fluor.
~4.8Mtpa
ore
Tailings
rejection
Leach Feed
Attrition
Acid Leaching,
Scrubbing
Neutralisation
of
feed
cDermitt will be a fully integrated operation producing
battery-grade Lithium arbonate for sale to US
customers.
~3.5Mtpa
M
C
Designed maximum annual production capacity of
47.5ktpa Lithium arbonate (limited by selected acid plant
capacity).
feed
~72%
mass
~92%
Li
recovery
Li Solution
Optimisation opportunities will be studied under the
recently announced cooperative research agreement with
the US Department of Energy (DoE) including:
roduct
pg
s
Ore u
W
Li Solution
recovery
C
By-p
Storage
Mg
Ion Exchange,
Mg & Ca
Li Crystallisation
Removal
Li2CO3
p
otential
g
p ms
Final Product
Drying,
radin
ater u e o
ti
Packing
i ation
Battery
47.5ktpa
grade
Total
Li2CO3
Process
of
product
Recovery
Streams
~85%
Process
p
Ste
s
W
aste
Streams
Note: Figures quoted reflect averages over first 10 years of commercial production
9
Inv
estor
n
Prese
i n
tat
o
F Highligh
P
S
ts
and
Ca
removal
Key PFS metrics demonstrate
(1)
encouraging economic outcomes
First 10 full years
Dimension
Next 30 years
Economic eval. period
Units
Pre-tax
Post-tax
Pre-tax
Post-tax
Pre-tax
Post-tax
Lithium
Short-term and long-term opportunities for investors
carbonate
carbonate
produced
Gross
revenue
average yearly EBITDA over first 10 years
Construction
capital
47.5 kt
of lithium per year
over the first 10 years
1000 jobs
during constuction
600 jobs
in operation
Payback
period
Sustaining
capital
Free
63-year
project life
66%
EBITDA margin in first
10 years
C1 costs
below
5 year
current spot prices
payback period from
production
$3.2B
17.9%
Post tax NPV
Post tax IRR
24,000
price
Lithium
$750M
$/t
cashflow
dry
tonnes
$M
475,000
1,295,355
1,796,169
11,400
31,089
43,108
$B
3.02
Years
5
$M
$M
102
7,108
406
6,629
18,680
508
14,022
23,080
18,061
C1 Costs*
$/t LCE
8,080
8,886
8,673
EBITDA
$M
7,562
19,578
27,530
EBITDA
EBITDA/
66%
63%
64%
Margin
Revenue
NPV (8%)
$M
3,895
3,229
IRR
%
18.1%
17.9%
*C1 cost includes operating costs for mining, processing, administration and product sales, after accounting for movements in inventory
related to ore stockpiles. It does not include 45X tax credits related to input costs (refer to PFS Announcement)
Economic Evaluation Period consists of construction, commissioning and ramp-up, followed by the first 40 full years of production.
10
Investor Presentation
PFS Highlights
Opportunities to
further optimise with
untapped optionality
Largest
LCE
Resource
in
US/North
America
3500
mcdermitT
While the PFS is robust, we have our eye on key
levers that can further de-risk the Project through
improvements to design, cost and sustainability, for
example:
Resources
(Mt)
3000
2500
thacker
pass
2000
clayton
valley
1500
nevada
1000
north
sonora
tlc
rhyolite
ridge
500
big
sandy
0
0
500
1000
Resources
1500
Lithium
2000
Grade
2500
3000
3500
(ppm)
Sources contained Appendix 2, bubble size based on contained LCE
11
Process optimisation
Exploration and infill drilling
Mining method optimisation
Extracting/refining co-products
Optimising attrition, leaching
and recovery processes to
improve cost and sustainability
outcomes. Opportunities
include further upgrading ore
prior to leaching to reduce acid
consumption.
With less than 11% of contained
lithium currently converted to
Ore Reserve, infill drilling aims to
boost grade continuity
confidence and may identify
higher-grade zones for
prioritised processing.
Further investigation around
mining methods, designs and
scheduling have the potential to
reduce costs and minimise
disturbance.
Magnesium sulphate and other
minerals within the deposit may
offer a supplementary cash flow,
subject to further exploration,
metallurgical testing and
feasibility studies.
Investor
Presentation
PFS
Highlights
Sustainability innovations
Further advancing
environmental sustainability
pathways, including reducing
water usage, by leveraging
strategic agreement with the
DoE, regional universities, and
(3)
the Oregon permitting agency
.
Corporations and government agencies are
striving to develop the US battery value chain
We are in a global race to compete in a
We will require all essential materials for
future where electric propulsion will
our national security to be produced
undoubtedly be a giant force in
here in the United States, creating
transportation.
millions and millions of new
manufacturing jobs.
President-elect Donald J Trump
Ford Motor Company
(source: address to New York Economic Club on 5 September 2024)
McDermitt poised to meet
medium-term deficits
(L)
The global lithium market is currently in surplus on the back of higher
Base Case, Lithium Market Balance, Unit kt LCE
100,000
prices during the 2022-23 peak
Current prices are below levels required to incentivise new production
0
Lithium producers seeing unsustainable returns in the short term are
-100,000
cutting production or deferring projects
Major players are making long-term plays during this down-cycle
-200,000
through strategic JVs and acquisitions (see slide 16)
Continuing robust global EV demand, with record-breaking 1.7 million
EVs sold in September 2024, growing by 22% year to date
(K)
-300,000
Forecast market deficits from 2028 are expected to drive prices
higher to levels required to incentivise new supply
(L)
-400,000
(K) Source: Rho Motion https://rhomotion.com/news/record-number-evs-sold-in-september/
-500,000
(L) Bechmark Minerals Intelligence Q3 2024 Dataset
-600,000
Presentation
What’s Our Market
Our pathway to
production is clear
14
Investor
Presentation
What’s
Our
Market
Activity
Orange bars indicate current critical path
Partnerships
Baseline Studies
NEPA* Permitting/
Record of Decision
Infill Drilling
2029
Pilot Test Work
Feasibility Study
FEED**
Project Funding
Final Investment Decision
2029
Construction/
Commissioning
2032
Operations
* National Environmental Policy Act
** Front-End Engineering Design
15
Investor Presentation
2025
Pathway Forward
Market momentum for lithium continues
with JVs and credible, strategic partnerships
Increasing market activity by large players
Development Funding
ioneer, Rhyolite Ridge Project,
Lithium Americas, Thacker Pass Project,
Rio Tinto to acquire Arcadium at 90% Premium
partners with Sibanye
partners with General Motors
Stillwater
$945M
$6.7B
$2.26B
Total commitment from
DOE loan
57% premium
Presentation
Sibanye Stillwater
DOE loan
Pre-Development Funding
Pilbara Minerals to acquire Latin Resources at
Investor
$650M
Total commitment from
General Motors
16
$700M
Pathway
Forward
-
Source
data
contained
2024
2023
2023
2024
2024
(Company - Partner)
(Company - Partner)
(Company - Partner)
(Company - Partner)
(Company - Partner)
$160M
C$116M
$100M
C$25M
A$8M
in
Appendix
3.
Partnerships will continue
to move us along the path to
production
Partnerships Criteria
PFS, led by Fluor Corporation and supported by
Cube Consulting, gives us confidence the Project is
worth pursuing further, as a huge resource with a
massive upside for investors and partners.
2023 MoU with POSCO Holdings to work jointly on the
project(4)
2024 strategic research and development agreement with
US DoE(3), in collaboration with US universities and Oregon
permitting agency
Specialist US advisors to target government funding
US Presence
US DoD grant application in progress for Feasibility Study*
co-funding
Deeper engagement with potential partners now PFS
is complete
Targeting partners with complementary skillsets
Partner/s to provide input on and funding for Feasibility
Study*
*including associated pre-development activities including infill drilling and metallurgical testwork
(4): Refer to JLL ASX release 13/02/2023 “MOU Executed with POSCO Holdings”
17
Investor Presentation
Pathway Forward
Into the Battery Value Chain
Major milestones and catalysts for the year ahead
(Q4) 2024
(Q1) 2025
(Q2) 2025
2025
Further work in 2025 to be considered
in parallel with partnership process:
Appoint strategic advisors to assist with
partnership process
Commence partnership
engagement process
Large infill exploration
drilling program
Potential DoD grant application award
(to co-fund next stage of work) (5)
Complete Exploration Plan of Operation (EPO) approvals for multi-year infill and exploration
drilling program
Comprehensive metallurgical
test work program
Commence Feasibility Study
(5): Refer to JLL ASX release 23/09/2024 “US Government Funding Update”.
18
Investor Presentation
Pathway Forward
Thank you
Further information
Ian Rodger
Chief Executive Officer
jindaleelithium.com
+61 8 9321 7550
jindaleelithium.com
Vrify 3D Presentation
View in Vrify
20
Investor Presentation
Vrivy 3D Presentation
Jindalee trades at an attractive
valuation relative to peers
84.3
Enterprise Value (US$)1 / Contained LCE2 in Resources (t) (4)
24.9
12.4
3.6
5.2
0.4
Jindalee Lithium
Century Lithium
Arizona Lithium
American Lithium
Lithium Americas
ioneer
McDermitt
Clayton Valley
Big Sandy + Prairie5
TLC + Falchani6
Thacker Pass
Rhyolite Ridge
Stage3
PFS
FS
Scoping
PFS
PEA
PEA
Construction
DFS
Enterprise Value (US$M)1
9
24
35
150
475
274
Project/s
Jindalee EV based an assumptions outlined on slide 5, converted to USD. All others sourced from S&P CapIQPro, 21 November 202
LCE = Lithium Carbonate Equivalent.
Source: various company reports.
Refer Appendix 1 and 2 for further details including data sources and resource classification breakdow
Arizona Lithium holds two development projects: a) Big Sandy Sediment Hosted project and b) Prairie Brine Direct Lithium Extraction projec
American Lithium holds two lithium development projects: a) Tonopah (TLC) Sediment hosted project and b) Falchini hard rock deposit. Metrics do not include Macusani Uranium deposit
21
Investor Presentation
Supporting Data
McDermitt: A highly competitive source
of lithium chemicals for the US Market
US$/t LCE (C1 Cost)
25,000
Thacker Pass
FS 2022
20,000
15,000
Rhyolite Ridge
FS 2021
McDermitt
PFS 2024
Silver Peak
10,000
5,000
0
1,500
3,000
Kt of LCE (2030)
McDermitt to be in the bottom half of the global cost curve on Lithium Carbonate (LCE) basis
Aligned to US energy security goals, McDermitt is expected to provide a large, long life domestic
source of lithium chemicals at highly competitive C1 operating cost relative to North American peers:
Source: All Cost curve data from Benchmark Minerals Intelligence 2030 C1 cost curve Q3 2024 dataset (incl. cost, production
and project details). McDermitt is not included in cost curve and location is illustrated via text only, based on McDermitt PFS
outputs
Comparable to North American DLE projects (mid-range)
North American Brines
At lower end of the range of forecasts for North American integrated spodumene producers
North American Direct Lithium Extraction (DLE)
Also cost competitive against Australian integrated spodumene producers
North American Spodumene Integrated
Lower cost supply (first quartile) is primarily from South American brine operations
North American Spodumene Non-Integrated
Australian Spodumene Integrated
Rest of World (RoW) Production
22
Investor Presentation
Supporting Data
Other
Operational
Financial
McDermitt comparison with Thacker Pass
Category
McDermitt PFS (November 2024)I
Thacker Pass FS (November 2022)I I
EBITDA Margin
64%
68%
Operating Cash Cost
US$8,673/t
(Defined as C1 cash costs)
US$7,198/t
(Phase 1 & 2)
US$3,229m
US$5,727m
(Phase 1 & 2, based on 2022 study. Excludes impact of Phase 1 increase of
US$662M)
17.9%
21.4%
(Phase 1 & 2, based on 2022 study. Excludes impact of Phase 1 increase of
US$662M)
Development capital
US$3,021m (inclusive of US$495m contingency)
Phase 1: US$2,930M (March 2024 update)
Phase 2: US$1,728M (based on 2022 FS)
Total Phase 1 & 2: US$4,650M
Avg. lithium Process Feed grade
1,967 ppm
3,070 ppm
Separation size / course gangue rejects
125 microns / 28%
75 microns / 34%
Average lithium recovery
84.4%
73.2%
Average Lithium Carbonate production
43.8 ktpa (47.5ktpa capacity & average over first 10 years)
Phase 1: 40ktpa (capacity)
Phase 2: 80Ktpa (capacity)
LOM: 66.8 ktpa
Lithium price assumed
US$24,000/t
US$24,000/t
Project Life
63 years
40 years
Reserves & Resource
Reserves: 2.34 Mt of contained LCE @ 1,340ppm Li
Resource: 21.5 Mt of contained LCEI I I @ 1,751ppm Li
Reserves: 3.7 Mt of contained LCE @ 3,160ppm Li
Resource: 19.1 Mt of contained LCEI I I @ 2,036 Li
Location
Oregon
Nevada
Engineering Consultants
Fluor Corporation and Cube Consulting
M3 Engineering & Technology
NPV8 % (post tax)
IRR (post ta
Share your feedback
Discover