Quarterly Activities Report - September 2024
Released
Released
Announcement PDF
JLL
JNDAF
31 October 2024
Engage with this announcement at the Jindalee Investor Hub
QUARTERLY ACTIVITIES REPORT
• Jindalee raises $6.1M via Placement, Convertible Notes and Entitlement Issue
• Funding enables completion of optimised McDermitt PFS and advances permitting and
engagement with US Government agencies, local community and strategic partners
• US Department of Energy to fund Cooperative Research and Development Agreement
focussed on reducing costs at McDermitt and minimising environmental impact
• McDermitt PFS progressing well and on schedule for delivery Q4 2024
US LITHIUM
McDermitt Lithium Project (Jindalee 100%)
In February 2023, Jindalee Lithium Limited (Jindalee or the Company) announced an updated Mineral
Resource Estimate (MRE) at Jindalee’s 100% owned McDermitt Lithium Project (McDermitt or the Project)
(Table 1)1.
The 2023 MRE for McDermitt contains a combined Indicated and Inferred Mineral Resource Inventory of 3.0
Billion tonnes at 1,340 ppm lithium (Li) for a total of 21.5 Million tonnes lithium carbonate equivalent (LCE)
at 1,000 ppm cut-off grade. At 21.5 Mt LCE, McDermitt is the largest lithium deposit in the United States (US)
by contained lithium in Mineral Resource, and a globally significant resource, with the deposit remaining open
to the west and south.
Cut-off Grade
(ppm Li)
1,000
Indicated Resource
Inferred Resource
Indicated and Inferred Resource
Tonnage
(Mt)
Li Grade
(ppm)
LCE
(Mt)
Tonnage
(Mt)
Li Grade
(ppm)
LCE
(Mt)
Tonnage
(Mt)
Li Grade
(ppm)
LCE
(Mt)
1,470
1,420
11.1
1,540
1,270
10.4
3,000
1340
21.5
Table 1 – Summary of 2023 McDermitt MRE1 at the reporting cut-off of 1,000 ppm. Note: totals may vary due to rounding
Metallurgical Test Work
The McDermitt flowsheet contemplates beneficiation of mined ore (to upgrade the leach head grade and
remove acid consuming gangue minerals) followed by acid leaching and subsequent purification steps to
produce battery grade lithium carbonate. The test work has been undertaken at Hazen Research Inc,
laboratories in Colorado, US and managed by global engineering, procurement, construction and maintenance
company Fluor Corporation (Fluor).
Jindalee Lithium Limited
ABN 52 064 121 133
Level 2, 9 Havelock Street, West Perth, WA, 6005
www.jindaleelithum.com
E: enquiry@jindaleelithium.com
P: +61 9321 7550
Visit Jindalee’s interactive
Investor Hub
https://investorhub.jindaleelithium.com/welcome
Initial acid leaching results announced in January 20242 demonstrated exceptional lithium extraction rates.
Tests were performed on two leach feeds: one with a 250 micron (µm) beneficiation cut size that underwent
leaching without additional grinding (250 µm leach feed), and another that was further ground to achieve
100% passing at 75 µm (75 µm leach feed). Using 500kg of acid per tonne of leach feed, both feeds
demonstrated very high lithium extraction rates, ranging from 88.8% to 99.1%. The leach test work extended
for up to four hours with most of the lithium extraction occurring in the first hour.
Further beneficiation test work during the June 2024 quarter identified several optimisation opportunities3.
Both lithium recovery through beneficiation (250 µm cut) and the lithium grade in the leach feed were shown
to be lower for Units 8 and 10 compared with Units 4 and 6. This suggested that focussing the plant design on
the two higher head grade Units may be more advantageous than a life-of-mine average of the four Units.
The focus on processing approximately equal shares of Units 4 and 6 also enabled the beneficiation cut size
to be reduced to 125 µm (Table 2). This resulted in lithium recovery through the beneficiation process being
maintained in excess of 91% with mass rejection improving 13%, calcium rejection improving 14% and
lithium grade to leach improving by 10% compared with the 250 µm cut. The overall upgrade in lithium to
leach grade compared with head grade is 29% (Unit 4) and 28% (Unit 6).
Unit
4
6
Average
Head Grade
(ppm Li)
1,785
1,819
Cut
(µm)
125
Mass
Rejection (%)
27.8
29.6
28.7
Beneficiation
Ca Rejection Li Recovery
(%)
(%)
47.1
93.4
70.6
90.0
58.9
91.7
Li to Leach
(ppm Li)
2,309
2,325
2,317
Table 2 – Summary of Beneficiation Results at 125 µm cut size - Units 4 and 6³
A 300kg composite sample (comprising Units 4, 6, 8 and 10) was leached and purified during the June 2024
quarter and on 31 July 2024 Jindalee announced first production of battery-grade Lithium Carbonate
(>99.5% Li2CO3) from McDermitt ore, validating the flowsheet developed for the Project4. Subsequently, the
Lithium Carbonate sample was further purified by Hazen with analysis by an external laboratory confirming
a grade of 99.98% Li2CO3 and minimal levels of contaminant elements.
POSCO Holdings (NYSE: PKX) (POSCO) has reported results from test work on beneficiated samples
(beneficiation cut size of 250 µm) shipped to Korea in the March 2024 quarter5. Test work undertaken by
POSCO included mechanical activation with salt leaching, and sulphuric acid leaching.
Mechanical activation test work on Unit 4 involved milling using either a planetary mill or a ball mill
accompanied by salt leaching using NaCl or MgCl2. This test work recorded a maximum extraction rate of
81.6% Li from a sample milled in a ball mill and leached with NaCl; however, POSCO notes that whilst reagent
costs were relatively low, reduction of milling time for amorphisation remains critical for this process to
become commercially viable.
Extraction rates achieved from sulphuric acid leaching were higher with 96.5% Li extracted from Unit 4
within 2 hours, and 96.3% Li extracted from Unit 6 in the same period. These extraction rates compare
closely with those achieved by Jindalee on 250 µm samples (96.8% from Unit 4 and 91.9% from Unit 6) at
similar acid dosages and leach times2. POSCO has advised that no further test work is currently planned.
Pre-Feasibility Study (PFS)
The McDermitt PFS commenced in June 2023 with Fluor appointed as lead engineer and Michael Elias
engaged as the Company’s Study Manager. Fluor has extensive experience with sediment hosted lithium
deposits in the US and has assembled a team of highly credentialled metallurgists and engineers to work on
the study.
Quarterly Activities Report – September 2024
Early July 202410, the Company announced that it was investigating the option to prioritise processing of
higher-grade Units 4 and 6 for a significant period from the start of operations, which together with other
opportunities not included in the initial PFS scope had the potential to significantly enhance Project returns.
Subsequently Cube Consulting completed mine schedule iterations, including developing schedules for
mining and processing Units 4 and 6 and stockpiling of Units 8 and 10 for potential treatment in later years,
with Cube Consulting currently working on preparation of a Maiden Ore Reserve Estimate for McDermitt.
Fluor continued to advance flowsheet design and process development based on processing Units 4 and 6
only, and an attrition cut size of 125 µm, with most engineering inputs completed and documented by late
September 2024. Other components of the PFS including permitting, hydrology, tailings and waste storage,
power and financial analysis were also nearing completion at the end of the period.
Permitting and Community Engagement
In May 2023 Jindalee announced that the Exploration Plan of Operations (EPO) for McDermitt, originally
submitted to the US Bureau of Land Management (BLM) in August 2022 (with additional information
provided early 2023), had been deemed complete6.
The public comment period on the EPO closed mid-September 2023 and the environmental review process
required by the National Environmental Policy Act (NEPA) commenced in January 2024. The final decision
of the NEPA assessment will be incorporated into the EPO, with this process expected to take up to 12
months. A draft of the Environmental Assessment (EA) was updated during the period to include further
mitigation measures following discussions with the BLM and additional State and Federal agencies, with the
EA expected to be submitted for public comment late Q4 2024 or early Q1 2025.
Once approved, the EPO will allow Jindalee to significantly increase on-site activity, including infill drilling to
provide additional geological and environmental data, together with fresh samples for geotechnical studies
and further metallurgical test work.
The Company has also entered into agreements with the nearby Fort McDermitt Paiute Shoshone Tribe
(FMPST), located approximately 30km east of the Project. These agreements form a crucial part of the
community engagement and permitting process.
The first agreement, a Communications Protocol, is designed to facilitate cooperation between the FMPST
and the Company and foster sharing of information and collaborative efforts between the parties. The
Communications Protocol also establishes a communication cadence between the parties to ensure open
dialogue on issues of common concern and interest.
The second agreement is a Cultural Study, Ethnobotanical Survey and Funding Agreement, which will allow
FMPST, in partnership with its consultants, to conduct studies in the Project area. These studies, which have
commenced, aim to identify culturally significant areas, plants and resources, ensuring that potential impacts
on the FMPST's cultural heritage are considered as part of Jindalee’s proposed activities under its EPO. Under
this agreement Jindalee will provide limited funds to FMPST to cover costs incurred as part of the studies.
Jindalee looks forward to working closely with the FMPST, and other Tribal groups, going forward.
The Company continues to build its US capability ahead of an expected increase in activity in CY 2025, with
an experienced ESG Manager appointed and expected to commence in November 2024.
Quarterly Activities Report – September 2024
US Government Support
Jindalee continues to engage with US Government agencies (both State and Federal) regarding opportunities
to advance the Project, including technical cooperation between agencies and the potential for US
Government funding for the Project. In April 2024 Jindalee provided an update on applications for nondilutive grant funding lodged with both the Department of Defense (DoD) and the Department of Energy
(DoE) (Battery Manufacturing and Recycling Grant)7.
If successful, the DoD grant application is expected to provide near term co-funding for an accelerated
Feasibility Study and associated drilling and test work at the Company’s McDermitt Lithium Project, whilst
the DoE grant application was for longer-term co-funding for the engineering, procurement, construction
and development of a lithium processing facility at McDermitt following completion of the Feasibility Study.
In September 2024 Jindalee was advised that the current DoE grant application was unsuccessful8; however,
the DoD grant application remains on foot, with any potential award decision expected late 2024 or early
2025.
Mid-September 2024 Jindalee announced that it had been approved by the DoE’s Office of Energy Efficiency
and Renewable Energy for a Cooperative Research and Development Agreement (CRADA)9. The CRADA aims
to develop cutting edge extraction methods for McDermitt designed to lower costs and minimise
environmental impact, including lowering water usage and acid consumption and reducing the footprint of
the Project, as well as exploring the potential for co-products. Research will be led by Ames National
Laboratory with other key members including the Oregon Department of Geology and Mineral Industries
(DOGAMI), Oregon State University, University of Nevada Reno, Lawrence Berkeley National Laboratory and
the National Energy Technology Laboratory.
Work undertaken under the CRADA will be funded by the DoE with Jindalee providing in-kind support,
including access to data, samples, and technical expertise. The CRADA has received strong support from
Senator Ron Wyden, the senior US Federal Senator for Oregon underlining the strategic importance of
McDermitt to the US. Notably, Senator Wyden is also the chair of the Senate Finance Committee as well as a
senior member of the Senate Energy and Natural Resources Committee.
INDUSTRY DEVELOPMENTS
The lithium carbonate price stabilised during the quarter as lithium producers scaled back production and
deferred capital expenditure to counter slower short-term demand, as high levels of inventory are wound
down. However, against this backdrop global EV sales remain strong and topped a record breaking 1.7
million units in September 2024, a new monthly record and representing a 22% year-to-date increase20.
The apparent bottom of the lithium price cycle has sparked consolidation in the sector and on 9 October 2024
Rio Tinto (ASX: RIO) announced the acquisition of Arcadium Lithium (ASX: LTM, Arcadium) for US$5.85 cash
per share, representing a 90% premium to Arcadium’s closing price on 4 October 202416. Rio Tinto noted
that the company “is confident in the long-term outlook for lithium, with more than 10% compound annual
growth rate in lithium demand expected through to 2040 leading to a supply deficit. With spot lithium prices
down more than 80% versus peak prices, this counter-cyclical acquisition comes at a time with substantial
long-term market and portfolio upside…”16
US Lithium Project Developments
Several positive developments regarding US lithium projects have been announced recently. On 25 October
2024 ioneer (ASX: INR) announced that its Rhyolite Ridge Lithium-Boron Project, located in Nevada (US),
had received its Record of Decision (ROD) from the BLM17. The ROD is the final permit approval required
Quarterly Activities Report – September 2024
from the US Federal Government with construction at Rhyolite Ridge planned to commence in 2025. This
approval comes ~8 years after ioneer’s first exploration drill hole in December 201621.
On 16 October 2024 Lithium Americas Corp (TSX: LAC, Lithium Americas) announced that General Motors
Holdings (GM) will acquire a 38% interest in the Thacker Pass lithium project (Nevada, US) for US$625M,
comprising US$430M cash to support the Phase 1 construction of Thacker Pass and a US$195M letter of
credit facility that can be used as collateral to support its DOE loan (discussed below)18. This is in addition to
GM’s Tranche 1 investment whereby GM invested US$320M in LAC shares in return for offtake from Phase 1
of the project, with GM’s direct and indirect investment in Thacker Pass now expected to total US$945M. The
Thacker Pass deposit (19.1Mt LCE23) is also located in the McDermitt Caldera, approximately 35km south of
Jindalee’s McDermitt deposit (21.5Mt LCE1), with both deposits being similar in terms of size and scale.
Subsequently on 28 October 2024 Lithium Americas advised that it had closed a concessional US$2.26B loan
from the DoE’s Loan Programs Office for financing the construction of the processing facilities at Thacker
Pass19. The interest rate on the loan is based on prevailing US Treasury rates (with 0% spread), with a long
tenor of 24 years from first draw of the loan. Lithium Americas expects to make a financial investment
decision and issue full notice to proceed for construction of Thacker Pass by the end of CY202419.
If both ioneer and Lithium Americas meet expected timeframes, there will be two significant US sedimentary
lithium deposits under construction in 2025.
US Tax Updates
In late October 2024, the US Department of Treasury issued final regulations22 for the Section 45X production
tax credits (PTC) under the Inflation Reduction Act 2022. Section 45X includes a 10% PTC based on eligible
operating costs incurred in the production of lithium carbonate (as an applicable critical mineral). Key
operating costs that now qualify for the PTC encompass labour, electricity, overheads and depreciation, with
expanded eligibility under the final regulations to include extraction (mining) costs for integrated operations
as contemplated for McDermitt, provided specific conditions are met. Additionally, the PTC covers costs of
materials used in the processing plant (e.g. reagents) if the suppliers do not claim 45X PTC. These revisions
mean that a significant portion of McDermitt’s operating costs are expected to qualify for the 45X PTC,
presenting potential benefits to project economics. Further analysis of the impact of these incentives will be
included in the upcoming McDermitt PFS.
Together, these recent US project developments and the updated 45X regulations underscore the US’
commitment to de-risking critical mineral supply chains via boosting domestic production. As a result,
McDermitt stands well-positioned as a future long-life US producer of lithium carbonate, aligned with
national objectives for critical mineral security.
CORPORATE
Capital Raising
During the period Jindalee raised approximately $6.1M via a combination of a Placement, Entitlement Issue
and Convertible Note (together, the Capital Raise)10, with potential to raise up to a further $9.0M in
Convertible Notes. The Capital Raise was cornerstoned by Mercer Street Global Opportunity Fund II and other
funds managed by US-based C/M Capital Partners (Mercer Street). The three components of the Capital Raise
are summarised below:
•
A Placement of ~$0.6M to Mercer Street, directors and management at $0.30 per fully paid ordinary
share (Share) with each 2 Shares accompanied by 1 listed Short-Term Option and 1 listed Long-Term
Option (Attaching Options):
Quarterly Activities Report – September 2024
•
•
Short-Term Option (JLLO): exercise price of $0.40 and expiry date of 30 June 2025
Long-Term Option (JLLOA): exercise price of $0.60 and expiry date of 30 June 2027
Placement Shares were issued to Mercer Street and management on 10 July 2024 following receipt of
funds, with participation in the Placement by Jindalee Directors approved at the Extraordinary
General Meeting (EGM) held 21 August 202411 and Shares issued shortly thereafter.
•
An Entitlement Issue to raise up to $3.1M from eligible shareholders on a 1 for 6 basis at $0.30 per
Share with Attaching Options being offered on the same ratio and the same terms issued to Placement
participants. Shareholders were also able to apply for any shortfall of new Shares offered in the
Entitlement Issue. The Entitlement Issue closed on 2 August 2024 with ~82.5% of the Shares available
under the Entitlement Issue taken up by Jindalee shareholders, raising ~$2.5M12.
•
An issue of Convertible Notes, each with a face value of $1.00, to Mercer Street for a total investment
of up to $12M in three or more tranches. Funds for the first tranche comprising an investment of
$1.5M were received early July 2024, with the second tranche (also $1.5M) approved at the EGM and
received in August 2024, with potential for additional funding of up to $9.0M by mutual agreement.
General
Jindalee’s 2024 Annual Report, together with the Company’s Corporate Governance Statement, were lodged
with ASX on 30 September 202413. Jindalee’s 2024 Annual General Meeting will be held on 26 November 2024
with the Notice of Meeting for the AGM despatched to shareholders on 25 October 202414.
In addition to its US lithium projects, Jindalee provides shareholders with indirect exposure to hard rock
lithium, gold, base and strategic metals, iron ore and magnesite in Australia through the Company’s holding
in Dynamic Metals Ltd (ASX: DYM or Dynamic). Further details on Dynamic’s activities can be found on
Dynamic’s website: https://dynamicmetals.com.au.
Jindalee currently has 71.4M shares on issue with cash and listed securities at 30 September 2024 of
approximately $6.0M15.
FINANCIAL COMMENTARY
The Quarterly Cashflow Report (Appendix 5B) for the period ending 30 September 2024 provides an
overview of the Company’s financial activities15.
Exploration and evaluation expenditure for the reporting period was $2,204k and was dominated by
expenditure on McDermitt. Net corporate expenditure was $743k. The total amount paid to directors of the
entity and their associates in the period (item 6.1 of the Appendix 5B) was $342k and includes directors’ fees,
consulting fees and superannuation.
Authorised for release by the Jindalee Board of Directors.
For further information please contact:
LINDSAY DUDFIELD
Executive Director
T:
+ 61 8 9321 7550
E:
enquiry@jindalee.net
Quarterly Activities Report – September 2024
IAN RODGER
Chief Executive Officer
T:
+ 61 8 9321 7550
E:
enquiry@jindalee.net
ADDITIONAL INFORMATION
Additional details including JORC 2012 reporting tables, where applicable, can be found in the ASX announcements
referenced in this report and announcements lodged with the ASX during the quarter:
References
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
Jindalee Lithium ASX announcement 27/02/2023: “Resource at McDermitt increases to 21.5 Mt LCE”
Jindalee Lithium ASX announcement 18/01/2024: “More Exceptional Metallurgical Results from McDermitt”
Jindalee Lithium ASX announcement 31/07/2024: “Quarterly Activities – June 2024”
Jindalee Lithium ASX announcement 31/07/2024: “Battery-Grade Lithium Carbonate Produced from McDermitt”
Jindalee Lithium ASX announcement 30/04/2024: “Quarterly Activities – March 2024”
Jindalee Lithium ASX announcement 16/05/2023: “McDermitt Progress Update”
Jindalee Lithium ASX announcement 30/04/2024: “Jindalee Advances US Government Funding for McDermitt”
Jindalee Lithium ASX announcement 23/09/2024: “US Government Funding Update”
Jindalee Lithium ASX announcement 16/09/2024: “Jindalee Secures Strategic Agreement with US Department of Energy”
Jindalee Lithium ASX announcement 04/07/2024: “JLL Secures Funding to Advance McDermitt Lithium Project”
Jindalee Lithium ASX announcement 21/08/2024: “Results of Meeting”
Jindalee Lithium ASX announcement 09/08/2024: “Results of Entitlement Issue”
Jindalee Lithium ASX announcement 30/09/2024: “Annual Report to Shareholders” and “Corporate Governance Statement”
Jindalee Lithium ASX announcement 25/10/2024: “Notice of Annual General Meeting/Proxy Form”
Jindalee Lithium ASX announcement 31/10/2024: “Quarterly Cashflow Report - September 2024”
Rio Tinto ASX announcement 09/10/2024: “Rio Tinto to acquire Arcadium Lithium”
ioneer ASX announcement 25/10/2024: “Rhyolite Ridge Project Receives Final Permit Approval”
https://lithiumamericas.com/news/news-details/2024/Unlocking-Thacker-Pass-General-Motors-to-Contribute-Combined625-Million-in-Cash-and-Letters-of-Credit-to-New-Joint-Venture-with-Lithium-Americas/
https://lithiumamericas.com/news/news-details/2024/Lithium-Americas-Closes-2.26-Billion-U.S.-DOE-ATVM-Loan/
https://investingnews.com/daily/resource-investing/battery-metals-investing/lithium-investing/lithium-forecast/
https://www.linkedin.com/posts/bernard-rowe-6219112b_major-lithium-mine-approved-in-nevada-in-activity7256028699353849856-CE2M?utm_source=share&utm_medium=member_desktop
https://www.federalregister.gov/documents/2024/10/28/2024-24840/advanced-manufacturing-production-credit
https://lithiumamericas.com/thacker-pass/overview/default.aspx
Competent Persons Statement
The information in this report that relates to Exploration Results, Mineral Resources or Ore Reserves is based on
information compiled by Mr. Lindsay Dudfield. Mr. Dudfield is a director, shareholder and consultant to the Company
and a Member of the Australasian Institute of Mining and Metallurgy and the Australian Institute of Geoscientists. Mr.
Dudfield has sufficient experience relevant to the styles of mineralisation and types of deposits under consideration, and
to the activity being undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Minerals Resources and Ore Reserves’ (JORC Code). Mr. Dudfield consents to
the inclusion in this report of the matters based on this information in the form and context in which it appears.
The information in this report that relates to the Exploration Target and the Mineral Resource Estimate for the
McDermitt deposit is based on information compiled by Mr. Arnold van der Heyden, who is a Member and Chartered
Professional (Geology) of the Australasian Institute of Mining and Metallurgy and a Director of H&S Consultants Pty Ltd.
Mr. van der Heyden has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of
the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code).
The Company confirms that it is not aware of any further new information or data that materially affects the information
included in the original market announcements by JLL listed above, and in the case of estimates of Mineral Resources,
that all material assumptions and technical parameters underpinning the estimates in the relevant market
announcements continue to apply and have not materially changed. To the extent disclosed above, the Company
confirms that the form and context in which the Competent Person’s findings are presented have not been materially
modified from the original market announcements.
Forward-Looking Statements
This document may contain certain forward-looking statements. Forward-looking statements include but are not
limited to statements concerning Jindalee’s current expectations, estimates and projections about the industry in which
Jindalee operates, and beliefs and assumptions regarding Jindalee’s future performance. When used in this document,
the words such as “anticipate”, “could”, “plan”, “estimate”, “expects”, “seeks”, “intends”, “may”, “potential”, “should”, and
similar expressions are forward-looking statements. Although Jindalee believes that its expectations reflected in these
forward-looking statements are reasonable, such statements are subject to known and unknown risks, uncertainties and
Quarterly Activities Report – September 2024
other factors, some of which are beyond the control of Jindalee and no assurance can be given that actual results will be
consistent with these forward-looking statements.
Such factors may include, among others, risks related to regulatory approvals of or in connection with the proposed
transaction, actual results of current or planned exploration activities, change in market conditions which affect the
completion of the transaction, obtaining appropriate approvals to undertake exploration activities in the portfolio of
projects, changes in exploration programs and budgets based upon the results of exploration, future prices of minerals
resources; grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining
government approvals or financing or in the completion of development or construction activities; movements in the
share price of investments and the timing and proceeds realised on future disposals of investments, the impact of the
COVID 19 pandemic as well as those factors detailed from time to time in the Company’s interim and annual financial
statements and reports, all over which are available for review on ASX at asx.com.au and OTC Markets at otcmarkets.com.
Although the Company has attempted to identify important factors that could cause actual actions, events or results to
differ materially from those described in forward-looking statements will prove to be accurate, as actual results and
future events could differ materially from those anticipated in such statements. Accordingly, readers should not place
undue reliance on forward-looking statements.
Quarterly Activities Report – September 2024
TENEMENT INFORMATION IN ACCORDANCE WITH LISTING RULE 5.3.3 As at 30 September 2024
Project
Tenement ID
Location
Status
Interest at
beginning of
Quarter
Interest at
end of
Quarter
McDermitt*
HTM 16-20, 24-35, 39-55, 59-77,
81-101, 105-125, 130-149, 152172, 176-195, 199-213, 217-225,
231-235, 238-242, 258-260, 340342, 348, 349, 355, 356, 362, 363,
369, 376-380, 387-391, 398, 399,
420-445, 448-456, 460-469, 480493, 496, 497, 500-517, 532-585,
685-687. HTX 1-113, 116-442.
Oregon, USA
Granted
100%
100%
Nevada, USA
Granted
100%
100%
Western Australia
Granted
20%
20%
HTM 586-682.
Nevada, USA
*
Clayton
North*
HTC 1-6, 12-18, 25-28.
Sherlock
E47/4345
Tenements held by Jindalee’s wholly owned US subsidiary, HiTech Minerals Inc.
Quarterly Activities Report – September 2024