McDermitt Lithium Project Pre-Feasibility Study
Released
Released
Announcement PDF
JLL
JNDAF
19 November 2024
McDERMITT PFS DEMONSTRATES
MULTI-DECADE COMPETITIVE
SOURCE OF US LITHIUM CARBONATE
Jindalee Lithium Limited (Jindalee, the Company; ASX: JLL, OCTQX: JNDAF) is pleased to advise that its recently
completed Pre-Feasibility Study (PFS), on the Company’s 100% owned McDermitt Lithium Project (currently the
largest lithium Resource in the USA) (McDermitt or the Project), has demonstrated strong economic returns over
an initial project life in excess of 40 yearsi
Highlights include:
•
Lithium Carbonate Production: Forecast production of 1.8 million tonnes battery grade Lithium Carbonate
over first 40 yearsi, supporting the growing US battery supply chain
•
Average Annual Lithium Carbonate Production:
✓ 47.5ktpa in the first 10 yearsi of operation (C1 unit cost US$8,080/t of lithium carbonate) ii
✓ 44.3ktpa in the first 40 yearsi of operation (C1 unit cost US$8,670/t of lithium carbonate)ii
•
Strong Financial Metrics (first 40 yearsiii): Ungeared, using flat US$24,000/t lithium carbonate priceiv
✓ Post-tax NPV8 of US$3,229Mv
✓ Post-tax IRR of 17.9%
✓ Payback period under 5 yearsvi
✓ NPV break even pricevii of ~US$14,600/t of lithium carbonate
Note: PFS price assumption for lithium carbonate is based on long term incentive priceiv which exceeds current Chinese
spot pricexiii
•
Generational Project with Life in Excess of 40 years: The PFS processing schedule (Processing Schedule)
supports a 63 year production life, however the production target and forecast financial information excludes
any production post 40 yearsi
•
Processing Studies and Capital Estimate prepared by Fluor Corporation (Fluor)viii: US$3.02B capital estimate,
including 21%ix contingency, prepared by Fluor - a leading US and global engineering and construction
company with deep experience in US sedimentary lithium projects
•
EBITDAx Marginxi: 66% over the first 10 yearsi of operations, with C1 costs in the bottom half of industryxii and
17% pre-tax net operating cashflow margins (including sustaining capital) at current spot pricesxiii
•
Maiden Probable Ore Reserve (JORC 2012) of 251Mt @ 1,751ppm lithium, containing 2.34Mt of Lithium
Carbonate Equivalent (LCE)xiv, accounts for 79%xv of forecast production in the PFS Processing Schedule but
represents only ~10% of current Mineral Resource on a contained LCE basis, highlighting future optionality
•
Cost Reduction and Sustainability: Opportunities for cost reduction and enhanced sustainability outcomes
through the recently announced strategic agreement with the US Department of Energyxvi
Jindalee Lithium Limited
ABN 52 064 121 133
Level 2, 9 Havelock Street, West Perth, WA, 6005
PO Box 1033, West Perth, WA 6872
www.jindaleelithum.com
E: enquiry@jindaleelithium.com
P: +61 9321 7550
F: +61 9321 7950
Visit Jindalee’s interactive
Investor Hub
https://investorhub.jindaleelithium.com/welcome
•
Potential Partnerships: PFS completion allows for deeper engagement with a broader pool of potential
strategic funding partners as well as the US Government agencies, which continue to actively support domestic
US critical minerals production
Jindalee’s CEO Ian Rodger Commented:
The completion of this PFS is a pivotal milestone for Jindalee and our wholly owned McDermitt Lithium Project,
underscoring McDermitt’s strategic potential as a large-scale, long-life competitive source of “American-made”
lithium chemicals for the US battery supply chain.
Among the study's key achievements is the successful bench-scale test work, which validated our flowsheet and
confirmed the production of battery-grade lithium carbonate with high recovery rates. While the PFS
demonstrates McDermitt’s compelling value, we remain committed to further enhancing cost efficiency and
sustainability as we responsibly advance the Project, delivering value for all stakeholders.
We are excited by the recent finalisation of Section 45X tax credit regulations under the Inflation Reduction Act,
which represents a significant shift in support for domestic lithium projects. By expanding eligible costs
specifically for integrated mining and refining operations—those producing a finished critical mineral product
like lithium carbonate—the policy now more effectively targets projects like McDermitt, which is designed to
produce battery-grade lithium chemicals domestically. This alignment with US energy security goals reflects a
commitment to reducing dependency on foreign suppliers by incentivising long-life, fully integrated supply chain
solutions within the US.
The completion of the PFS delivers, for the first time, the production metrics and cost estimates needed to engage
meaningfully with potential strategic partners, accelerating discussions with a solid technical and financial
foundation. It also provides a catalyst for re-engaging with US government agencies on potential future funding,
building on our current Department of Defense grant application, which could co-fund the next phase of
development.
Jindalee has an exciting 12 months ahead as we advance our Exploration Plan of Operations, targeted for midCY2025. This will enable a significant infill drilling campaign to inform a future feasibility study and associated
test work. With a robust PFS and encouraging early interest from prospective partners, we look forward to
building on this momentum as we evaluate the next steps for McDermitt.
I extend my sincere thanks to the Jindalee team and our consulting partners, Fluor Corporation and Cube
Consulting, whose expertise was instrumental in delivering the PFS.”
Jindalee is pleased to release the McDermitt PFS attached below.
Authorised for release by the Jindalee Board of Directors. For further information please contact:
LINDSAY DUDFIELD
Executive Director
T:
+ 61 8 9321 7550
E:
enquiry@jindaleelithium.com
McDermitt Pre-Feasibility Study – November 2024
IAN RODGER
Chief Executive Officer
T:
+ 61 8 9321 7550
E:
enquiry@jindaleelithium.com
Cautionary Statement
The full 63 year PFS Processing Schedule is based on processing 79% Probable Ore Reserves, 3% Indicated Resources
and 18% Inferred Resources. The production target set out in the PFS covering the initial 40 yearsi of the Processing
Schedule is based on 82% inventory within the Indicated Mineral Resources category, with the balance (18%) being
classified within the Inferred Mineral Resources category. As the Inferred Mineral Resources make up only 5% of the
Processing Schedule over the first 20 years of full production (post ramp-up), Jindalee is satisfied that the Inferred
Mineral Resources are not a determining factor in the viability of the Project. There is a low level of geological confidence
associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production target itself will be realised.
Shareholders and prospective investors should be aware that the PFS does not include any forecast financial
information in respect of the period after the initial 40 years of the Processing Schedule (post single commission and
ramp up year), as Jindalee cannot, at this stage, provide forecast financial information for that subsequent period.
This announcement and information, opinions or conclusions expressed in the course of this announcement contain
forward looking statements and forecast financial information. Jindalee has concluded that it has a reasonable basis for
those forward looking statements and forecast financial information, including the use of a flat US$24,000/t lithium
carbonate price, the production target set out in the PFS and the financial information on which it is based. The basis
for that conclusion is contained throughout this announcement and all material assumptions, including the JORC
modifying factors, upon which the forward looking statements and forecast financial information are based, are
disclosed in this announcement. However, such forecasts, projections and information are not a guarantee of future
performance and involve unknown risks and uncertainties. Actual results and developments will almost certainly differ
materially from those expressed or implied. There are a number of risks, both specific to Jindalee, and of a general
nature, which may affect the future operating and financial performance of Jindalee, and the value of an investment in
Jindalee including and not limited to title risk, renewal risk, economic conditions, stock market fluctuations, commodity
demand and price movements, timing of access to infrastructure, timing of environmental approvals, regulatory risks,
operational risks, reliance on key personnel, Reserve estimations, cultural resources risks, foreign currency
fluctuations, and mining development, construction and commissioning risks.
To achieve the range of outcomes indicated in the PFS, the PFS estimates that funding in the order of $3.02B in
construction capital will be required. Shareholders and investors should be aware that there is no certainty that Jindalee
will be able to raise the required funding when needed and it is possible that such funding may only be available on
terms that may be highly dilutive or otherwise adversely affect Jindalee shareholders’ exposure to the Project
economics. Specifically, as outlined in this PFS, Jindalee intends to pursue potential third party partnerships (with
parties who have the potential to be joint venture partners in the Project) to advance the Project and may pursue other
value realisation strategies such as a sale or partial sale of the Project or underlying future commodity streams. If it does
so, such arrangements may materially reduce Jindalee’s proportionate ownership of the Project and/ or adversely affect
Jindalee shareholders’ exposure to the Project economics.
i Full years of production post 1 year commissioning and ramp up period)
ii C1 costs post 1 year ramp up, before any relevant tax credits are applied to input costs. Based on PFS Processing
Schedule
iii PFS economic evaluation period consists of construction, commissioning & ramp-up, followed by first 40 full years of
production (Economic Evaluation Period)
iv Price assumption of $24,000/t battery grade lithium carbonate (99.5% battery grade) based on ~17% discount to
Benchmark Mineral Intelligence long term forecast (Q2 2024 dataset)
v Post tax figures include estimated 45X tax credits as outlined in section 10.2.1
vi From first production
vii Price at which NPV8 is greater than zero
viii Ranked as No. 1 on ENR’s 2023 list of the Top Contractors in the in the refining, petrochemical, and mining sectors
ix Contingency ($495M) divided by pre-production capital excluding mining, owner’s costs and contingency ($2,353M)
x EBITDA is defined as Earnings Before Interest, Tax, Depreciation and Amortisation. Shareholders and prospective
investors should be aware that certain financial measures, including EBITDA and EBITDA Margin, included in this
announcement are ‘non-IFRS financial information’ under ASIC Regulatory Guide 230: “Disclosing non-IFRS financial
information” published by ASIC and also “Non-GAAP” financial measures within the meaning of Regulation G under the
US Securities Exchange Act of 1934 and are not recognised under the AAS or IFRS. Non-IFRS and Non-GAAP financial
measures do not have standardised meanings prescribed by AAS or IFRS and may not be comparable to similarly titled
McDermitt Pre-Feasibility Study – November 2024
measures used by other entities, nor should the information be construed as an alternative to other financial measures
determined in accordance with AAS or IFRS. Shareholders and investors are therefore cautioned not to place undue
reliance on any non-IFRS financial information contained in this announcement.
xi Calculated as EBITDA/Revenue
xii Benchmark Mineral Intelligence 2030 C1 Lithium Carbonate Equivalent Cost Curve on LCE basis (Q2 2024 dataset).
Note that break even NPV8 price is ~$14,600/t, which is currently above current Chinese spot price (see below)
xiii $10,888/t from Shanghai Metal Markets Lithium Carbonate Index (Battery Grade), delivered to China, VAT inclusive.
As at 14 November 2024
xiv Lithium Carbonate Equivalent (LCE) is a standard measure that expresses the amount of lithium in terms of lithium
carbonate. One tonne of lithium metal is equivalent to 5.323 tonnes of LCE
xv 63 year PFS Processing Schedule ore tonnage breakdown: 79% Probable Ore Reserve, 3% Indicated and 18% Inferred
Mineral Resources.
xvi Refer to JLL ASX announcement dated 24 September 2024 “Jindalee Secures Strategic Agreement with US Department
of Energy”
McDermitt Pre-Feasibility Study – November 2024
Executive Summary
All values are presented in US$ unless otherwise stated.
Jindalee’s 100% owned McDermitt Lithium Project (McDermitt or the Project) is located approximately 35km west of
the town of McDermitt, straddling the Oregon – Nevada border in the United States of America (United States or US).
The Project covers 13,606 acres covered by Unpatented Mining Claims.
The Project occurs in an extinct volcanic caldera, with lithium mineralisation hosted in a sequence of flat lying lakebed
sediments overlying a basaltic basement. Recent geological work has defined a consistent stratigraphic sequence
comprising 11 distinct geological units. Four of these units (labelled Units 4, 6, 8 and 10) contain elevated lithium grades
above 1,000ppm. Only Units 4 and 6 were considered for processing in the PFS due to their higher grade and recovery
characteristics.
The Project has a published Mineral Resource Estimate (MRE) of 3,000Mt at an average grade of 1,340ppm lithium for
a contained LCE of 21.5Mt1, making McDermitt currently the largest lithium resource in the United States. Jindalee
subsequently released an Exploration Target Range2 (ETR) highlighting further potential upside at the Project. Both the
MRE and ETR have a reporting cut-off grade of 1,000ppm lithium.
Jindalee is committed to ensuring the responsible development of the McDermitt Lithium Project, focusing on
minimising environmental impact and delivering long-term economic and social benefits to local communities, industry,
government, and Native American stakeholders.
The PFS envisions a conventional open-pit mining method, with a low strip ratio and no blasting required due to the
soft and friable nature of the ore and waste material. The pit designs and mining schedule were developed by Cube
Consulting, treating only Units 4 and 6 as ore, although Units 8 and 10 are economically viable and may be incorporated
into the production schedule in future study phases.
The PFS also supports publication of a Maiden Probable Ore Reserve (JORC 2012), also developed by Cube Consulting,
of 251Mt of Ore grading an average of 1,751ppm lithium for 2.34Mt of contained LCE (only ~10% of the lithium
contained in the MRE). 79% of the PFS mining schedule comprises Probable Ore Reserves, 3% Indicated Mineral
Resources, with the balance (18%) being Inferred Resources, weighted towards the back end of the schedule.
The processing flowsheet consists of ore beneficiation (attrition scrubbing), sulphuric acid leaching, purification and
lithium carbonate precipitation. This flow sheet positions the Project as a fully integrated domestic US battery grade
lithium carbonate producer. Bench scale metallurgical test work has successfully validated all steps of the flowsheet,
achieving high overall lithium recoveries of 81-89% (varying by Unit). Additionally, this test work successfully produced
a 99.8% pure lithium carbonate, comfortably meeting battery grade industry standards.
The process plant is designed to have lithium carbonate production capacity of 47.5ktpa. The Project is forecast to
produce at this rate for its first 10 full years of production, before declining slowly as the feed grade declines (assuming
no further high-grade ore is defined), producing circa 1.8Mt of Lithium Carbonate over an initial 40 year production life
(post commissioning and ramp-up), which forms the basis of the PFS Economic Evaluation. The full 63 year PFS
Processing Schedule is based on processing 79% Probable Ore Reserves, 3% Indicated Resources and 18% Inferred
Resources, with forecast total production of 2.5Mt of Lithium Carbonate.
Onsite non-process infrastructure was defined by Fluor, with grid power supply, tailings and waste storage, and water
supply scope definition completed by experienced specialist engineering firms. Fluor consolidated the non-process
infrastructure capital cost estimate on a common basis. The Project benefits from access to the power grid and US
highway systems via the town of McDermitt, while the nearest railhead at Winnemucca, 120km south of the town of
McDermitt, provides access to the extensive North American rail system.
The pre-production capital cost for the Project is estimated at $3.02B, classified as a Class 4 estimate under the
Association for the Advancement of Cost Engineering (AACE) estimate classification system, with an accuracy of +35%/25%. The estimate base date is Q1 CY2024. The capital cost estimate considers all execution-phase costs (post final
investment decision), such as engineering procurement, construction and commissioning, to bring the Project into
operation. Construction and commissioning are assumed to be undertaken over a three-year period, with pre-strip
mining commencing in the third year.
The operating cost estimate for the Project has been classified as Class IV (AACE) and is based on Q1 CY2024 pricing.
The cash operating cost for the first 10 years of full production is estimated at $8,760 per tonne of lithium carbonate,
1 Refer to JLL ASX announcement dated 27 February 2023
2 Refer to JLL ASX announcement dated 21 November 2023
McDermitt Pre-Feasibility Study – November 2024
with a C1 cost of $8,080 per tonne over the same period. The largest portion of operating costs is attributed to the
process plant, derived from a Fluor-developed cost model.
The PFS results demonstrate a robust financial case for the Project under base case assumptions. Key financial and
operational metrics are summarised in Table 0-1 and reinforce the long life, high margin nature of the Project. The
Project maintains average EBITDA margins above 64% over the Economic Evaluation Period (including commissioning
and ramp-up year, plus 40 full years of production), with C1 costs in the bottom half of industry cost curve3, 17% pretax net operating cashflow margins (including sustaining capital) at current lithium carbonate spot prices 4 and payback
within the first five years of production. Additionally, a number of future opportunities have been identified during the
PFS, which have the potential to materially improve Project economics through process optimisation and potential
production of co-products.
The Chinese lithium carbonate spot price, which peaked at approximately $77,000/t5 in Q4 2022, has declined
significantly to its current level of around $10,900/t due to a market surplus. As a result, the current spot price is below
both the long-term incentive price and McDermitt’s NPV8 breakeven price of ~$14,600/t6. However, market deficits are
projected to emerge in the early 2030s, coinciding with McDermitt’s anticipated development timeline. Accordingly, the
PFS financial analysis uses a lithium carbonate price assumption of $24,000/t, representing a 17% discount to
Benchmark Mineral Intelligence’s Q2 2024 long-term incentive price forecast.
Key sensitivities for Project post-tax NPV and cash flow were tested. As is typical for most resource projects, value was
most sensitive to revenue (as a proxy for lithium price, lithium recovery and/or lithium head grade). The Project showed
the lowest sensitivity to construction capital costs, given the long life and large revenues generated.
McDermitt is expected to be a significant employer in the region, with approximately 1,000 direct jobs to be created
during the Project’s construction period (estimated at three years) and approximately 600 direct full-time roles during
its operating life.
The Project requires a comprehensive set of regulatory approvals at Federal, State, and County levels, and a reputable
US based consultant has been engaged to guide the permitting process. Importantly, no issues have been identified to
date that are expected to prevent the Project’s approval. Strong, bipartisan recognition of the strategic importance of
domestically produced lithium provides further confidence in the Project’s ultimate approval. The permitting strategy
developed for the PFS targets full approval within five years, which aligns with the timeline for the next phase of
technical studies to support a final investment decision for the Project by the end of CY2029.
As a US-based project expected to produce battery-grade lithium carbonate, McDermitt holds a range of strategic
advantages, bolstered by bipartisan support to de-risk critical mineral supply chains. The US government is actively
supporting domestic critical minerals through various funding mechanisms, and the Inflation Reduction Act 2022 (IRA)
incentivises sourcing battery materials from domestic or allied nations, excluding China. With the US set to increase
requirements for domestic sourcing to qualify for IRA tax credits, McDermitt's position as a future domestic producer
of lithium carbonate makes it highly attractive to potential offtake and strategic partners.
In the short term, Jindalee’s focus is on securing pre-development funding, which includes exploring US government
funding sources and forming strategic partnerships. These partnerships will de-risk the Project technically and
commercially, paving the way for subsequent development financing. Early engagement with potential partners has
been encouraging, and further engagement is set to increase following the completion of the PFS. Additionally, Jindalee
has established a Cooperative Research and Development Agreement with the US Department of Energy and has applied
for support from the US Department of Defense to co-fund a Feasibility Study and associated drilling and test work,
further enhancing the Project's financing prospects.
3 Based on the first 10 years of commercial production and Benchmark Mineral Intelligence 2030 C1 Lithium Carbonate
Equivalent Cost Curve (Q2 CY2024 dataset)
4 US$10,888/t from Shanghai Metal Markets Lithium Carbonate Index (Battery Grade), delivered to China, VAT inclusive.
As at 14 November 2024
5 Benchmark Minerals Intelligence Q2 2024 dataset
6 Price at which NPV8 is greater than zero
McDermitt Pre-Feasibility Study – November 2024
6
Table 0-1: Key PFS Physical and Financial Metrics
Physicals and Production Summary
First 10 Full Years
Economic Evaluation Period
(Project life incl. construction, commissioning/
ramp-up and first 40 full yrs of production)
Ore processing rate
4.8 to 5.3 Mt per annum
Ore tonnes processed
48.5Mt
203Mt
Average lithium feed grade
2,146ppm
1,967ppm
Average lithium recovery
85.8%
84.4%
Average lithium carbonate production
47,500t per annum
43,800t per annum
Total lithium carbonate production1
475,000t
1,796,169t
Pre-Production Capital Cost
Pre-production capital
$2,377M
Contingency
$495M
Owner’s costs
$149M
Total2
$3,021M
Payback period3
5 years
Financial Results4
First 10 full years
Economic Evaluation Period
Revenue
$11,400M
$43,108M
Sustaining capital
$102M
$508M
Net free cashflow: Pre-tax
$7,108M
$23,080M
Net free cashflow: Post-tax
$6,629M
$18,061M
$8,080/t LCE
$8,673/t LCE
66%
64%
C1 Costs5
EBITDA Margin6
Discounted Cashflow4, 7: Pre-tax
$3,895M
Discounted Cashflow4, 7: Post-tax
$3,229M
IRR4: Pre-tax
18.1%
IRR4: Post-tax
17.9%
Notes: (1) Annual figures rounded to nearest 100t, total rounded to nearest 500t. (2) Totals may not sum due to rounding. (3) From
commencement of production (4) At $24,000/t lithium carbonate price. (5) C1 cost includes operating costs for mining, processing,
administration and product sales, after accounting for movements in inventory related to ore stockpiles. (6) Calculated as EBITDA /
Revenue. (7) 8% real discount rate.
McDermitt Pre-Feasibility Study – November 2024
7
Table of Contents
Executive Summary ............................................................................................................................................................. 5
1
Project Details ...................................................................................................................................................... 11
1.1
Project Setting......................................................................................................................................................................... 11
1.2
Project Tenure ........................................................................................................................................................................ 11
2
Mineral Resource ................................................................................................................................................ 12
2.1
Background .............................................................................................................................................................................. 12
2.2
Mineral Resource Estimate (MRE) ................................................................................................................................. 12
2.3
Exploration Target Range .................................................................................................................................................. 13
3
Mining ..................................................................................................................................................................... 14
3.1
Overview ................................................................................................................................................................................... 14
3.2
Pit Design .................................................................................................................................................................................. 14
3.3
Mine Schedule ......................................................................................................................................................................... 16
3.4
Ore Reserve Estimate .......................................................................................................................................................... 18
3.5
Mining Fleet ............................................................................................................................................................................. 18
3.6
Mining Cost Estimate ........................................................................................................................................................... 19
3.7
Pit Dewatering ........................................................................................................................................................................ 19
4
Metallurgy ............................................................................................................................................................. 20
4.1
Overview ................................................................................................................................................................................... 20
4.2
Sample Selection .................................................................................................................................................................... 20
4.3
Mineralogy and Ore Characteristics .............................................................................................................................. 20
4.4
Beneficiation / Attrition Scrubbing ............................................................................................................................... 20
4.5
Sulphuric Acid Leach Test Work ..................................................................................................................................... 21
4.6
Purification and Lithium Carbonate Precipitation .................................................................................................. 21
5
Process Plant ........................................................................................................................................................ 22
5.1
Overview ................................................................................................................................................................................... 22
5.2
Flowsheet and Process Description ............................................................................................................................... 22
5.3
Design Criteria ........................................................................................................................................................................ 23
5.4
Production Profile ................................................................................................................................................................. 23
5.5
Waste Storage ......................................................................................................................................................................... 23
6
Infrastructure....................................................................................................................................................... 24
6.1
Overview .............................................................................................................................................................................