Quarterly Activities Report - December 2024
Released
Released
Announcement PDF
JLL
JNDAF
Engage with this announcement at the Jindalee Investor Hub
31 January 2025
QUARTERLY ACTIVITIES REPORT
• McDermitt PFS confirms 63 year life, producing 1.8Mt Lithium Carbonate over first 40
years
• Strong financial metrics with C1 costs $8,670/t for first 40 years and 5 year pay-back
• Maiden Ore Reserve of 2.34Mt LCE1 uses only ~10% of current Resource (21.5Mt LCE2)
• Excellent potential to further reduce capital and operating costs as well increase
production
•
Engagement with funding partners and US Government agencies accelerating post PFS
US LITHIUM
McDermitt Lithium Project (Jindalee 100%)
Pre-Feasibility Study (PFS) - Overview
On 19 November 2024 Jindalee Lithium Limited (Jindalee or the Company) announced the results of the PFS
on Jindalee’s McDermitt Lithium Project (McDermitt or the Project)1. The PFS represents the culmination of
over 18 months of detailed metallurgical testwork and engineering and related studies managed by the
Jindalee team with key support from Fluor Corporation (Fluor), a leading US and global engineering and
construction company with deep experience in US sedimentary lithium projects, Cube Consulting and
specialist US and Australian consultants. Highlights of the PFS are summarised in Table 1 and include:
(all data mentioned below in relation to the PFS is sourced from JLL ASX announcement: “McDermitt Lithium Project Pre-Feasibility
Study” dated 19 November 2024)
•
•
Lithium Carbonate Production: Forecast production of 1.8 million tonnes battery grade Lithium
Carbonate (LC) over first 40 years, supporting the growing US battery supply chain
Average Annual Lithium Carbonate Production:
o
o
•
47.5ktpa in the first 10 years of commercial operation (C1 unit cost US$8,080/t of lithium
carbonate)
44.3ktpa in the first 40 years of commercial operation (C1 unit cost US$8,670/t of lithium
carbonate)
Strong Financial Metrics (first 40 years): Ungeared, using flat US$24,000/t lithium carbonate price
o
o
o
Post-tax NPV8 of US$3,229M
Post-tax IRR of 17.9%
Payback period under 5 years
Jindalee Lithium Limited
ABN 52 064 121 133
Level 2, 9 Havelock Street, West Perth, WA, 6005
www.jindaleelithum.com
E: enquiry@jindaleelithium.com
P: +61 9321 7550
Visit Jindalee’s interactive
Investor Hub
https://investorhub.jindaleelithium.com/welcome
•
•
•
•
Generational Project with Life in Excess of 40 years: The PFS Processing Schedule supports a 63 year
production life (including commissioning and ramp-up), however it is important to note that the
production target and forecast financial information excludes any production post 40 years of
commercial operation
Processing Studies and Capital Estimate prepared by Fluor: US$3.02B capital estimate, including
21% contingency
EBITDA Margin: 66% over the first 10 years of operations, with C1 costs in the bottom half of industry
and 17% pre-tax net operating cashflow margins (including sustaining capital) at November 2024 spot
prices
Maiden Probable Ore Reserve (JORC 2012) of 251Mt @ 1,751ppm lithium, containing 2.34Mt1 of
Lithium Carbonate Equivalent (LCE), accounts for 79% of forecast production in the PFS Processing
Schedule but represents only ~10% of current Mineral Resource (MRE)2 on a contained LCE basis,
highlighting future optionality
Table 1 – Key PFS Physical and Financial Metrics
Physicals and Production Summary
First 10 Full Years
Economic Evaluation Period
(Project life incl. construction, commissioning/
ramp-up and first 40 full yrs of production)
Ore processing rate
Ore tonnes processed
Average lithium feed grade
Average lithium recovery
Average lithium carbonate production
Total lithium carbonate productioni
Pre-Production Capital Cost
48.5Mt
4.8 to 5.3 Mt per annum
2,146ppm
1,967ppm
47,500t per annum
43,800t per annum
85.8%
84.4%
475,000t
1,796,169t
Pre-production capital
US$2,377M
Owner’s costs
US$149M
Contingency
US$495M
Totalii
Payback periodiii
Financial Resultsiv
203.0Mt
US$3,021M
First 10 full years
5 years
Economic Evaluation Period
Revenue
US$11,400M
US$43,108M
Net free cashflow: Pre-tax
US$7,108M
US$23,080M
Sustaining capital
Net free cashflow: Post-tax
C1 Costsv
EBITDA Marginvi
Quarterly Activities Report – December 2024
US$102M
US$6,629M
US$8,080/t LCE
66%
US$508M
US$18,061M
US$8,670/t LCE
64%
Discounted Cashflowiv, vii: Pre-tax
US$3,895M
Discounted Cashflowiv, vii: Post-tax
US$3,229M
IRRiv: Pre-tax
18.1%
IRRiv: Post-tax
17.9%
Notes: (i) Annual figures rounded to nearest 100t, total rounded to nearest 500t. (ii) Totals may not sum due to rounding. (iii) From
commencement of production. (iv) At US$24,000/t lithium carbonate price. (v) C1 cost includes operating costs for mining, processing,
administration and product sales, after accounting for movements in inventory related to ore stockpiles. (vi) Calculated as EBITDA /
Revenue. (vii) 8% real discount rate. Refer to Jindalee’s ASX announcement dated 19 November 20241 for further details.
PFS – Discussion
Jindalee’s 100% owned McDermitt Lithium Project is located approximately 35km west of the town of
McDermitt, straddling the Oregon and Nevada border in the United States of America (US).
The Project occurs in the McDermitt Caldera, an extinct volcanic structure, with lithium mineralisation
hosted in a sequence of flat lying lakebed sediments overlying a basaltic basement. Recent geological work
has defined a consistent stratigraphic sequence comprising 12 distinct geological units. Four of these units
(Units 4, 6, 8 and 10) contain elevated lithium grades above 1,000ppm. Only Units 4 and 6 were considered
for processing in the PFS due to their higher grade and recovery characteristics.
The current (2023) MRE for McDermitt contains a combined Indicated and Inferred Mineral Resource
Estimate of 3.0 Billion tonnes at 1,340ppm lithium (Li) for a total of 21.5 Million tonnes LCE at 1,000ppm cutoff grade2 (see Table 2). At 21.5Mt LCE, McDermitt is one of the largest lithium deposits in the US by contained
lithium in Mineral Resource, and a globally significant resource, with the deposit remaining open, particularly
to the west.
Table 2 – Summary of 2023 McDermitt MRE2. Note: totals may vary due to rounding
Cut-off Grade
(ppm Li)
1,000
Indicated Resource
Inferred Resource
Indicated and Inferred
Resource
Tonnage
(Mt)
Li
Grade
(ppm)
LCE
(Mt)
Tonnage
(Mt)
Li Grade
(ppm)
LCE
(Mt)
Tonnage
(Mt)
Li Grade
(ppm)
LCE
(Mt)
1,470
1,420
11.1
1,540
1,270
10.4
3,000
1340
21.5
The PFS envisions a conventional open-pit mining method, with a low strip ratio and no blasting required
due to the soft and friable nature of the ore and waste material. The pit designs and mining schedule were
developed by Cube Consulting, treating only Units 4 and 6 as ore, although Units 8 and 10 are economically
viable and may be incorporated into the production schedule in future study phases.
The PFS supported publication of a Maiden Probable Ore Reserve, also developed by Cube Consulting, of
251Mt of Ore grading an average of 1,751ppm lithium for 2.34Mt of contained LCE (Table 3), representing
only ~10% of the lithium contained in the MRE. 79% of the PFS mining schedule comprises Probable Ore
Reserves, 3% Indicated Mineral Resources with the balance (18%) being Inferred Resources, weighted
towards the back end of the schedule.
Table 3 – Summary of 2024 McDermitt Reserve1. Note: totals may vary due to rounding
Cut-off Grade
(ppm Li)
1,000
Quarterly Activities Report – December 2024
Probable Reserve
Tonnage (Mt)
Li Grade (ROM-ppm)
LCE (Mt)
251
1,751
2.34
The processing flowsheet consists of ore beneficiation (attrition scrubbing), sulphuric acid leaching,
purification and lithium carbonate precipitation (Figure 1). This flowsheet positions the Project as a fully
integrated domestic US battery grade lithium carbonate producer. Bench scale metallurgical test work has
successfully validated all steps of the flowsheet, achieving high overall lithium recoveries of 81-89% (varying
by Unit). Additionally, this test work successfully produced a 99.8% pure lithium carbonate, comfortably
meeting battery grade industry standards3.
Figure 1 – Simplified Process Flowsheet
The process plant is designed to have lithium carbonate production capacity of 47.5ktpa. The Project is
forecast to produce at this rate for its first 10 full years of production, before declining slowly as the feed
grade declines (assuming no further high-grade ore is defined), producing circa 1.8Mt of Lithium Carbonate
over an initial 40 year production life post ramp up and commissioning, which forms the basis of the PFS
Economic Evaluation.
The full 63 year PFS Processing Schedule is based on processing 79% Probable Ore Reserves, 3% Indicated
Resources and 18% Inferred Resources, with forecast total production of 2.5Mt of Lithium Carbonate (Figure
2).
Quarterly Activities Report – December 2024
Figure 2 – PFS Processing Schedule by Ore Classification
Excluded from Economic
Evaluation
Annual Processing Feed Proportion
100%
75%
50%
25%
0%
1
11
21
31
41
51
61
Processing Year
Indicated Processed
Inferred Processed
Onsite non-process infrastructure was defined by Fluor, with grid power supply, tailings and waste storage,
and water supply scope definition completed by experienced specialist engineering firms. Fluor consolidated
the non-process infrastructure capital cost estimate on a common basis. The Project benefits from access to
the power grid and US highway systems via the town of McDermitt, while the nearest railhead at
Winnemucca, 120km south of the town of McDermitt, provides access to the extensive North American rail
system.
The pre-production capital cost for the Project is estimated at US$3.02B, classified as a Class 4 estimate under
the Association for the Advancement of Cost Engineering (AACE) estimate classification system, with an
accuracy of +35%/-25%. The estimate base date is Q1 CY2024. The capital cost estimate considers all
execution-phase costs (post final investment decision), such as engineering procurement, construction and
commissioning, to bring the Project into operation. Construction and commissioning are assumed to be
undertaken over a three-year period, with pre-strip mining commencing in the third year.
The operating cost estimate for the Project has been classified as Class IV (AACE) and is based on Q1 CY2024
pricing. The cash operating cost for the first 10 years of full production is estimated at US$8,760 per tonne
of lithium carbonate, with a C1 cost of US$8,080 per tonne over the same period. The largest portion of
operating costs is attributed to the process plant, derived from a Fluor-developed cost model.
The PFS results demonstrate a robust financial case for the Project under base case assumptions. Key
financial and operational metrics are summarised in Table 1 and reinforce the long life, high margin nature
of the Project. The Project maintains average EBITDA margins above 64% over the 40-year Economic
Evaluation Period, with C1 costs in the bottom half of industry cost curve, 17% pre-tax net operating cashflow
margins (including sustaining capital) at November 2024 lithium carbonate spot prices and payback within
the first five years of production (Figure 3).
Quarterly Activities Report – December 2024
Figure 3 – Annual and Cumulative Cashflow during Economic Evaluation Period
(excluding end of life rehabilitation costs)
20,000
$1,500
15,000
$1,000
10,000
5,000
$0
0
-5,000
-$500
Sales Revenue
Capital Costs
Tax Credits
Cum Cash Flow (RH Axis)
-$1,000
-$1,500
-$2,000
1
6
11
16
21
-10,000
Operating Costs
Income Tax
Net Post Tax Cash Flow
26
31
36
US$M
US$M
$500
-15,000
-20,000
41
-25,000
Project Year
Additionally, a number of future opportunities have been identified during the PFS, which have the potential
to materially improve Project economics through process optimisation and potential production of coproducts. These include opportunities for cost reduction and enhanced sustainability outcomes through the
recently announced strategic agreement with the US Department of Energy4.
Key sensitivities for Project post-tax NPV and cash flow were tested. As is typical for most resource projects,
value was most sensitive to revenue (as a proxy for lithium price, lithium recovery and/or lithium head
grade). The Project showed the lowest sensitivity to construction capital costs, given the long life and large
revenues generated.
Jindalee is committed to ensuring the responsible development of the McDermitt Lithium Project, focusing
on minimising environmental impact and delivering long-term economic and social benefits to local
communities, industry, government, and Native American stakeholders. McDermitt is expected to be a
significant employer in the region, with approximately 1,000 direct jobs to be created during the Project’s
construction period (estimated at three years) and approximately 600 direct full-time roles during its
operating life.
The Project requires a comprehensive set of regulatory approvals at Federal, State, and County levels, and a
reputable US based consultant has been engaged to guide the permitting process. Importantly, no issues have
been identified to date that are expected to prevent the Project’s approval. Strong, bipartisan recognition of
the strategic importance of domestically produced lithium provides further confidence in the Project’s
ultimate approval. The permitting strategy developed for the PFS targets full approval within five years,
which aligns with the timeline for the next phase of technical studies to support a final investment decision
for the Project by the end of CY2029.
As a US-based project expected to produce battery-grade lithium carbonate, McDermitt holds a range of
strategic advantages, bolstered by bipartisan support to de-risk critical mineral supply chains. The US
government is actively supporting domestic critical minerals through various funding mechanisms, and the
Inflation Reduction Act 2022 (IRA) incentivises sourcing battery materials from domestic or allied nations,
excluding China. With the US set to increase requirements for domestic sourcing to qualify for IRA tax credits
and increase tariffs on imported lithium chemicals (especially from China), McDermitt's position as a future
domestic producer of lithium carbonate makes it highly attractive to potential offtake and strategic partners.
In the short term, Jindalee’s focus is on securing pre-development funding, which includes exploring US
government funding sources and forming strategic partnerships. These partnerships will de-risk the Project
technically and commercially, paving the way for subsequent development financing. Early engagement with
potential partners has been encouraging, and further engagement has increased following the completion of
Quarterly Activities Report – December 2024
the PFS. Additionally, Jindalee has established a Cooperative Research and Development Agreement with the
US Department of Energy4 and has applied for a grant from the US Department of Defense (DoD) to co-fund
a Feasibility Study and associated drilling and test work5, further enhancing the Project's financing prospects.
Permitting and Community Engagement
In May 2023 Jindalee announced that the Exploration Plan of Operations (EPO) for McDermitt, originally
submitted to the US Bureau of Land Management (BLM) in August 2022 (with additional information
provided early 2023), had been deemed complete6.
The public comment period on the EPO closed mid-September 2023 and the environmental review process
required by the National Environmental Policy Act (NEPA) commenced in January 2024. The final decision
of the NEPA assessment will be incorporated into the EPO, with this process expected to take up to 12
months. A draft of the Environmental Assessment (EA) was updated during the period to include further
mitigation measures following discussions with the BLM and additional State and Federal agencies, with the
EA expected to be submitted for public comment Q1 2025.
Once approved, the EPO will allow Jindalee to significantly increase on-site activity, including infill drilling to
provide additional geological and environmental data, together with fresh samples for geotechnical studies
and further metallurgical test work.
In October 2024 the Company announced that it had entered into agreements with the nearby Fort
McDermitt Paiute Shoshone Tribe (FMPST), located approximately 30km east of the Project7. These
agreements form a crucial part of the community engagement and permitting process.
The first agreement, a Communications Protocol, is designed to facilitate cooperation between the FMPST
and the Company and foster sharing of information and collaborative efforts between the parties. The
Communications Protocol also establishes a communication cadence between the parties to ensure open
dialogue on issues of common concern and interest.
The second agreement is a Cultural Study, Ethnobotanical Survey and Funding Agreement, which will allow
FMPST, in partnership with its consultants, to conduct studies in the Project area. These studies aim to
identify culturally significant areas, plants and resources, ensuring that potential impacts on the FMPST's
cultural heritage are considered as part of Jindalee’s proposed activities under its EPO. Under this agreement
Jindalee will provide limited funds to FMPST to cover costs incurred as part of the studies. Jindalee looks
forward to working closely with the FMPST, and other Tribal groups, going forward.
The Company continues to build its US capability ahead of an expected increase in activity in 2025, including
appointment of experienced Environmental, Social, and Governance (ESG) Manager Sandra Carson who
commenced in November 2024. Ms Carson will focus on advancing the federal and state permitting programs
at McDermitt, developing robust community engagement programs for McDermitt and surrounding
communities (including interested Tribal groups), and developing industry-leading ESG policies and
procedures specific to exploration activities, which would be among the first in the industry to focus on early
stage exploration.
US Government Support
Jindalee continues to engage with US Government agencies (both State and Federal) regarding opportunities
to advance the Project, including technical cooperation between agencies and the potential for US
Government funding for the Project.
In September 2024 Jindalee announced that it had been approved by the Department of Energy’s (DoE) Office
of Energy Efficiency and Renewable Energy for a Cooperative Research and Development Agreement
Quarterly Activities Report – December 2024
(CRADA)4. The CRADA aims to develop cutting edge extraction methods for McDermitt designed to lower
costs and minimise environmental impact, including lowering water usage and acid consumption and
reducing the footprint of the Project, as well as exploring the potential for co-products. Research is being led
by Ames National Laboratory with other key members including the Oregon Department of Geology and
Mineral Industries (DOGAMI), Oregon State University, University of Nevada Reno, Lawrence Berkeley
National Laboratory and the National Energy Technology Laboratory.
Work undertaken under the CRADA is being funded by the DoE with Jindalee providing in-kind support,
including access to data, samples, and technical expertise. In October 2024, Jindalee hosted a contingent of
researchers from the consortium at the McDermitt Project location to further project understanding and
develop mineralogical characterisation and genesis models. This foundational work will be leveraged in
developing and refining future novel lithium extraction methodologies from the McDermitt ore, which could
potentially further optimise the McDermitt flowsheet.
Also in September 2024, Jindalee confirmed that an application for non-dilutive grant funding lodged with
the DoD remained on foot5. If successful, the DoD grant application is expected to provide near term cofunding for an accelerated Feasibility Study and associated drilling and test work at McDermitt, with any
potential award decision now expected early 2025, once policy settings under President Trump have been
confirmed.
Following his election victory in November 2024, President Trump was inaugurated as President of the
United States on 21 January 2025. The Trump administration has expressed strong support for increasing
US production of critical minerals and reducing reliance on China, which currently dominates global supply
chains for these essential materials, including lithium. Several policy initiatives are anticipated to advance
this objective, such as:
•
•
•
Increased tariffs on Chinese imports: Tariffs as high as 60% have been proposed to incentivise
domestic production8.
Streamlined regulation in the critical mineral sector: Efforts include fast-tracking permitting for new
projects, supported by two executive orders issued on President Trump’s first day in office9,10,11.
Enhanced financing and tax incentives: Ongoing support for domestic critical minerals projects,
bolstered by an additional executive order issued on President Trump’s first day in office11.
As a future large-scale, long-life producer of “American-made” lithium chemicals for the US battery supply
chain, the McDermitt Lithium Project is well placed to capitalise on the Trump administration’s strong
support for domestic critical minerals projects and US energy security.
INDUSTRY DEVELOPMENTS
The price of battery grade lithium carbonate hovered around US$10,000/t at the end of the quarter as lithium
producers continued to scale back production and defer projects and capital expenditure on the back of weak
pricing. However, EV sales remained strong with 17.1 million units sold globally in 2024 (up 25% on 2023),
including 1.9 million units in December 2024 alone, marking a fourth consecutive monthly sales record12.
Recent research by Benchmark Mineral Intelligence (Benchmark) notes that despite current oversupply and
low prices for battery materials significant deficits are forecast in the next 10 years13. Benchmark expects
that lithium will be the bottleneck for the growth of the battery industry and predicts that 2.7Mt lithium
(LCE) will need to be mined to meet demand in 2030, requiring upstream investment of US$51B13.
Quarterly Activities Report – December 2024
US Lithium Project Developments
Strong Electrical Vehicle OEM (original equipment manufacturer) and US Government support for US
domestic lithium projects continued during the period, underlying the importance of sediment hosted
deposits as a source of lithium for the US battery industry.
On 25 October 2024 ioneer Ltd (ASX: INR) announced that its Rhyolite Ridge Lithium-Boron Project, located
in Nevada (US), had received its Record of Decision (ROD) from the BLM14. The ROD is the final permit
approval required from the US Federal Government with construction at Rhyolite Ridge planned to
commence in 2025. Subsequently, on 17 January 2025, the US DoE’s Loan Programs Office announced the
closing of a US$996M loan guarantee (including US$968 million of principal and US$28 million of capitalised
interest) to ioneer Ltd to finance the on-site processing of lithium carbonate15.
On 23 December 2024 Lithium Americas Corp (TSX: LAC, Lithium Americas) announced the closing of its
agreement with General Motors Holdings (GM) whereby GM acquired a 38% interest in the Thacker Pass
lithium project (Nevada, US) for US$625M, comprising US$430M cash to support the Phase 1 construction of
Thacker Pass and a US$195M letter of credit facility16. The letter of credit is designed to be used as collateral
to support its US$2.26B loan from the DoE to finance construction of the processing facilities at Thacker Pass
which closed 28 October 202417.
This is in addition to GM’s Tranche 1 investment whereby GM invested US$320M in LAC shares in return for
offtake from Phase 1 of the project, with GM’s total direct and indirect investment in Thacker Pass now
US$945M18. Lithium Americas expects to make a financial investment decision and issue full notice to
proceed for construction of Thacker Pass in early 202518.
On 7 January 2025 Lithium Americas announced that total resources (Measured, Indicated and Inferred) at
Thacker Pass had increased to 5,767.5Mt @ 2,175ppm Li for 66.1Mt LCE at a cut-off grade of 858ppm Li, with
reserves (Proven and Probable) increasing to 1,056.7Mt @ 2,540ppm Li for 14.3Mt LCE, making Thacker
Pass the largest lithium deposit in the world18,19. Lithium Americas also announced plans to increase
production at Thacker Pass over 5 phases to reach 160,000tpa lithium carbonate, for a total capital
investment of US$12.4B (excluding sustaining capital) over a base case Life of Mine of 85 years.
Thacker Pass and McDermitt are both sediment hosted lithium deposits located in the McDermitt Caldera,
approximately 35km apart. The McDermitt deposit remains open with excellent potential for shallow highgrade intercepts outside of current resources, and the recent increase in resources and reserves at Thacker
Pass reinforces the significant potential of the district.
Recent US project developments and favourable changes to tax credit regulations20 underscore the US’
commitment to de-risking critical mineral supply chains via boosting domestic production, with McDermitt
well-positioned as a future long-life US producer of lithium carbonate, aligned with national objectives for
critical mineral, manufacturing and energy security.
CORPORATE
Jindalee’s 2024 Annual General Meeting was held on 26 November 2024 (AGM) with all resolutions approved
overwhelmingly21. The Company thanks shareholders for their attendance and ongoing support.
The following securities were issued during the period:
•
•
•
•
2,000,000 unlisted options to directors following shareholder approval at the Company’s AGM;
2,226,148 shares to noteholders on the conversion of 467,124 convertible notes;
4,500,000 unlisted options to employees; and
2,374,948 performance rights to employees.
Quarterly Activities Report – December 2024
In addition to its US lithium projects, Jindalee provides shareholders with indirect exposure to mineral
projects in Australia through the Company’s holding in Dynamic Metals Ltd (ASX: DYM or Dynamic). Further
details on Dynamic’s activities can be found on Dynamic’s website:
https://dynamicmetals.com.au.
Jindalee currently has 73.6M shares on issue, with cash and listed securities at 31 December 2024 of
approximately $5.5M22.
FINANCIAL COMMENTARY
The Quarterly Cashflow Report (Appendix 5B) for the period ending 31 December 2024 provides an overview
of the Company’s financial activities22.
Exploration and evaluation expenditure for the reporting period was $568k and was dominated by
expenditure on McDermitt. Net corporate expenditure was $935k. The total amount paid to directors of the
entity and their associates in the period (item 6.1 of the Appendix 5B) was $156k and includes directors’ fees,
consulting fees and superannuation.
Authorised for release by the Jindalee Board of Directors.
For further information please contact:
LINDSAY DUDFIELD
Executive Director
T:
+ 61 8 9321 7550
E:
enquiry@jindaleelithium.com
Quarterly Activities Report – December 2024
IAN RODGER
Chief Executive Officer
T:
+ 61 8 9321 7550
E:
enquiry@jindaleelithium.com
ADDITIONAL INFORMATION
Additional details including JORC 2012 reporting tables, where applicable, can be found in the ASX announcements
referenced in this report and announcements lodged with the ASX during the quarter:
References
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
Jindalee Lithium ASX announcement 19/11/2024: “McDermitt Lithium Project Pre-Feasibility Study”
Jindalee Lithium ASX announcement 27/02/2023: “Resource at McDermitt increases to 21.5 Mt LCE”
Jindalee Lithium ASX announcement 31/07/2024: “Battery-Grade Lithium Carbonate produced from McDermitt”
Jindalee Lithium ASX announcement 16/09/2024: “Jindalee Secures Strategic Agreement with US Department of Energy”
Jindalee Lithium ASX announcement 23/09/2024: “US Government Funding Update”
Jindalee Lithium ASX announcement 16/05/2023: “McDermitt Progress Update”
Jindalee Lithium ASX announcement 23/09/2024: “Quarterly Activities Report – September 2024”
https://www.pbs.org/newshour/economy/trump-favors-huge-new-tariffs-how-do-they-work
https://www.bloomberg.com/news/articles/2024-12-18/trump-team-eyes-ev-subsidy-cuts-in-plan-to-reshape-autoindustry
Declaring a National Energy Emergency – The White House
Unleashing American Energy - The White House
https://rhomotion.com/news/over-17-million-evs-sold-in-2024-record-year/
https://source.benchmarkminerals.com/article/battery-cathode-material-deficits-continue-to-be-expected-by-the-end-ofdecade
https://wcsecure.weblink.com.au/pdf/INR/02871214.pdf
https://www.energy.gov/lpo/articles/doe-announces-996-million-loan-guarantee-ioneer-rhyolite-ridge-advance-domestic
https://lithiumamericas.com/news/news-details/2024/Lithium-Americas-Announces-Closing-of-Thacker-Pass-JointVenture-with-General-Motors/default.aspx
https://lithiumamericas.com/news/news-details/2024/Lithium-Americas-Closes-2.26-Billion-U.S.-DOE-ATVM-Loan/
https://s203.q4cdn.com/835901927/files/doc_presentations/2025/01/Technical-Report-December-2024.pdf
https://lithiumamericas.com/news/news-details/2025/Lithium-Americas-Increases-Mineral-Resource-and-Reserve-forThacker-Pass/default.aspx
https://www.federalregister.gov/documents/2024/10/28/2024-24840/advanced-manufacturing-production-credit
Jindalee Lithium ASX announcement 26/11/2024: “Results of Meeting”